2810 S MANSFIELD AVE 90016
Certificate Information: 2810 S MANSFIELD AVE 90016
- Application / Permit
- 20016-70000-00015
- Plan Check / Job No.
- B20SL00001
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- CONVERT GARAGE TO STORAGE WITH HALF BATH.
- Permit Issued
- Issued on 1/2/2020
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 2/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 1/2/2020 | TEODORO DIAZ RODRIGUEZ |
| Issued | 1/2/2020 | LADBS |
| CofO in Progress | 5/15/2021 | DAVID FEILER |
| Permit Finaled | 2/17/2023 | DANIEL ORRANTE |
| CofO Issued | 2/17/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/17/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/8/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Final | 1/8/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 1/8/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 1/29/2020 | Not Ready for Inspection | DAVID CHAN |
| BUILDING-Rough-Frame | 2/13/2020 | Corrections Issued | DAVID CHAN |
| Rough-Elec/Plmb/HVAC | 2/13/2020 | Corrections Issued | DAVID CHAN |
| ELECTRICAL-Rough | 12/4/2020 | No Access for Inspection | DAVID CHAN |
| PLUMBING-Rough | 12/4/2020 | No Access for Inspection | DAVID CHAN |
| BUILDING-Rough-Frame | 12/9/2020 | Partial Approval | DAVID CHAN |
| ELECTRICAL-Rough | 12/9/2020 | Partial Approval | DAVID CHAN |
| PLUMBING-Rough | 12/9/2020 | Partial Approval | DAVID CHAN |
| PLUMBING-Rough | 2/2/2021 | No Access for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 2/5/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Pre-Inspection | 2/19/2021 | Conditional Approval | JOSEPH MCGARRY |
| Pre-Inspection | 4/28/2021 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 5/12/2021 | Approved | DAVID FEILER |
| Final | 5/12/2021 | OK to Issue CofO | DAVID FEILER |
| Smoke Detectors | 5/12/2021 | Approved | DAVID FEILER |