800 W OLYMPIC BLVD 4th Floor 90015
Certificate Information: 800 W OLYMPIC BLVD 4th Floor 90015
- Application / Permit
- 20016-40000-07864
- Plan Check / Job No.
- B20SP00297
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Interior, non-structural tenant improvement to the 4th floor of (E) Office Building (12,766 SF). Scope of work to include partitions, ceiling grid, finishes, and millwork. No change in use or occupancy.
- Permit Issued
- Issued on 4/24/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/19/2021
Permit Application Status History
| Submitted | 3/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | CHRISTOPHER KOMANCHECK |
| Corrections Issued | 3/19/2020 | CHRISTOPHER KOMANCHECK |
| Plan Check Approved | 4/14/2020 | FERNANDO FLORES |
| Issued | 4/24/2020 | LADBS |
| Building Plans Picked Up | 4/27/2020 | APPLICANT |
| Permit Finaled | 5/18/2021 | DANIEL COLLINS |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 3/26/2020 | MICAELA TORRES-GIL |
| Specific Plan | Cleared | 3/26/2020 | MOHAMMAD HASAN |
| Redevelopment Project Area | Cleared | 3/31/2020 | DAVID URITA |
Contact Information
| Architect | Kamus,, John Howard; Lic. No.: C20397 | 5364 EVENING SKY DRIVE SIMI VALLEY, CA 93063 |
| Contractor | Environmental Contracting Corporation; Lic. No.: 491028-B | 880 EAST 1ST STREET LOS ANGELES, CA 90012 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 2/1/2021 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 3/2/2021 | Approved | KATY RAMIREZ |
| T-Bar Ceiling | 3/22/2021 | Approved | DANIEL COLLINS |
| Light Gage Steel Frame | 4/8/2021 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 4/12/2021 | Approved | JONATHAN QUACH |
| Final | 5/18/2021 | Permit Finaled | DANIEL COLLINS |
| Green Building Final | 5/18/2021 | Approved | DANIEL COLLINS |
| SGSOV-Seismic Gas S/O Valve | 5/18/2021 | SGSOV Approved | DANIEL COLLINS |
| Smoke Detectors | 5/18/2021 | Approved | DANIEL COLLINS |