1380 W SEPULVEDA ST 90732

Certificate Information: 1380 W SEPULVEDA ST 90732

Application / Permit
20016-40000-07637
Plan Check / Job No.
B20SP00292
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior and exterior remodel to (E) SFD with attached garage. Scope of work to include converting portion of living area to bathroom. All work per engineered design. COMPLY WITH DEPARTMENT ORDER effective date 03/26/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
Permit Issued
Issued on 5/6/2020
Issuing Office
Metro
Current Status
Permit Finaled on 7/16/2021

Permit Application Status History

Submitted 3/17/2020 APPLICANT
Assigned to Plan Check Engineer 3/17/2020 JASON JANGADA
Corrections Issued 3/17/2020 JASON JANGADA
Plan Check Approved 4/29/2020 FERNANDO FLORES
Issued 5/6/2020 LADBS
Building Plans Picked Up 5/7/2020 APPLICANT
Permit Finaled 7/16/2021 ANDREW BEELI

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/29/2020 JASON JANGADA

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/8/2020 Conditional Approval ANDREW BEELI
BUILDING-Rough-Frame 5/11/2020 Not Ready for Inspection ANDREW BEELI
Footing/Foundation/Slab 5/11/2020 Approved ANDREW BEELI
BUILDING-Rough-Frame 5/18/2020 Not Ready for Inspection ANDREW BEELI
Gas Test 5/18/2020 Partial Inspection ANDREW BEELI
Rough-Elec/Plmb/HVAC 5/18/2020 Partial Inspection ANDREW BEELI
HVAC-Rough 5/21/2020 Approved ANDREW BEELI
PLUMBING-Rough 5/21/2020 Approved ANDREW BEELI
Insulation 5/29/2020 Approved ANDREW BEELI
Drywall Nailing 6/3/2020 Approved ANDREW BEELI
Shower Pan 6/15/2020 Approved PAUL BECKER
Interior/Exterior Lathing 6/29/2020 Approved ANDREW BEELI
Final 11/6/2020 Not Ready for Inspection ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 11/6/2020 SGSOV Not Ready ANDREW BEELI
Smoke Detectors 11/6/2020 Approved ANDREW BEELI
ELECTRICAL-Rough 11/18/2020 Approved ANDREW BEELI
PLUMBING-Rough 11/18/2020 Approved ANDREW BEELI
BUILDING-Rough-Frame 11/19/2020 Approved ANDREW BEELI
Final 3/22/2021 Corrections Issued ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 3/22/2021 SGSOV Approved ANDREW BEELI
Final 7/16/2021 Permit Finaled ANDREW BEELI