828-832 W 17TH ST 90731
Certificate Information: 828-832 W 17TH ST 90731
- Application / Permit
- 20016-40000-06812
- Plan Check / Job No.
- B20SP00255
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Conversion of (E) storage space (334 SF) on first floor of (E) two-story Duplex with attached garage to Accessory Dwelling Unit (334 SF) per GCS 65852.2(e)(1)(C).
- Permit Issued
- Issued on 11/10/2021
- Issuing Office
- Current Status
- CofO Issued on 4/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | JASON JANGADA |
| Corrections Issued | 3/27/2020 | JASON JANGADA |
| Quality Review Completed | 4/3/2020 | CHRISTOPHER KOMANCHECK |
| Applicant returned to address corrections | 4/15/2020 | JASON JANGADA |
| Plan Check Approved | 4/17/2020 | JASON JANGADA |
| Building Plans Picked Up | 4/22/2020 | APPLICANT |
| Green Plans Picked Up | 4/22/2020 | APPLICANT |
| Issued | 11/10/2021 | APPLICANT |
| CofO in Progress | 4/21/2022 | JOHN KLARIN |
| CofO Issued | 4/25/2022 | DEROLD HAUFF |
| Permit Finaled | 4/25/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/6/2020 | CHINH DINH |
| Sewer availability | Cleared | 4/6/2020 | CHINH DINH |
| Tenant Habitability Plan | Cleared | 4/6/2020 | STEVEN HOFSTAD |
| Green Code | Cleared | 4/13/2020 | RICHARD GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2020 | CHINH DINH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/24/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| ELECTRICAL-Final | 11/24/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| ELECTRICAL-Rough | 11/24/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 11/24/2021 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 11/24/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Rough | 11/24/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| HVAC-Final | 11/24/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| HVAC-Rough | 11/24/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Final | 11/24/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 11/24/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 11/24/2021 | SGSOV Not Ready | ANSON MAGLASANG |
| Smoke Detectors | 11/24/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Pre-Inspection | 3/7/2022 | Partial Inspection | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 3/9/2022 | Partial Approval | ANSON MAGLASANG |
| Green Building Rough | 3/9/2022 | Approved | ANSON MAGLASANG |
| Rough-Elec/Plmb/HVAC | 3/9/2022 | Approved | ANSON MAGLASANG |
| Insulation | 3/11/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 3/15/2022 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 3/29/2022 | Approved | ANSON MAGLASANG |
| Final | 3/29/2022 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 3/29/2022 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV Approved | ANSON MAGLASANG |
| Smoke Detectors | 3/29/2022 | Approved | ANSON MAGLASANG |
| Final | 4/15/2022 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/20/2022 | Approved | ANSON MAGLASANG |
| Final | 4/20/2022 | OK to Issue CofO | JOHN KLARIN |