932 W MILLMARK GROVE ST 90731
Certificate Information: 932 W MILLMARK GROVE ST 90731
- Application / Permit
- 20016-40000-03559
- Plan Check / Job No.
- B20SP00128
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Exterior and interior alteration to (E) SFD with attached garage. Scope of work to include enclosing (E) covered entry way, converting two bedrooms into one bedroom with walk in closet, remodel bathroom, and close one window. All work per engineered design.
- Permit Issued
- Issued on 2/18/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/10/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | JASON JANGADA |
| Corrections Issued | 2/6/2020 | JASON JANGADA |
| Plan Check Approved | 2/13/2020 | CHRISTOPHER KOMANCHECK |
| Issued | 2/18/2020 | LADBS |
| CofO in Progress | 5/30/2020 | JOHN KLARIN |
| Permit Finaled | 6/10/2020 | BOB DUNN |
| CofO Issued | 6/10/2020 | BOB DUNN |
| Permit Finaled | 6/10/2020 | BOB DUNN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/13/2020 | JONATHAN HOM |
Contact Information
| Engineer | Saleh,, Zouheir Toufic; Lic. No.: C42881 | 1304 CORTE MALTERA COSTA MESA, CA 92626 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/26/2020 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 2/26/2020 | Approved | ANSON MAGLASANG |
| PLUMBING-Rough | 2/26/2020 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 3/3/2020 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Rough | 3/3/2020 | Approved | ANSON MAGLASANG |
| Green Building Rough | 3/3/2020 | Approved | ANSON MAGLASANG |
| Insulation | 3/3/2020 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 3/3/2020 | Partial Approval | ANSON MAGLASANG |
| METHANE-Rough | 3/3/2020 | Approved | ANSON MAGLASANG |
| Drywall Nailing | 3/6/2020 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Final | 4/7/2020 | Approved | JOHN KLARIN |
| Final | 4/7/2020 | Conditional Approval | JOHN KLARIN |
| Green Building Final | 4/7/2020 | Approved | JOHN KLARIN |
| PLUMBING-Final | 4/7/2020 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 4/7/2020 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 4/7/2020 | Approved | JOHN KLARIN |
| Final | 5/29/2020 | OK to Issue CofO | JOHN KLARIN |