932 W MILLMARK GROVE ST 90731

Certificate Information: 932 W MILLMARK GROVE ST 90731

Application / Permit
20016-40000-03559
Plan Check / Job No.
B20SP00128
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Exterior and interior alteration to (E) SFD with attached garage. Scope of work to include enclosing (E) covered entry way, converting two bedrooms into one bedroom with walk in closet, remodel bathroom, and close one window. All work per engineered design.
Permit Issued
Issued on 2/18/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/10/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/6/2020 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 JASON JANGADA
Corrections Issued 2/6/2020 JASON JANGADA
Plan Check Approved 2/13/2020 CHRISTOPHER KOMANCHECK
Issued 2/18/2020 LADBS
CofO in Progress 5/30/2020 JOHN KLARIN
Permit Finaled 6/10/2020 BOB DUNN
CofO Issued 6/10/2020 BOB DUNN
Permit Finaled 6/10/2020 BOB DUNN

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/13/2020 JONATHAN HOM

Contact Information

Engineer Saleh,, Zouheir Toufic; Lic. No.: C42881 1304 CORTE MALTERA      COSTA MESA, CA 92626

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/26/2020 Conditional Approval ANSON MAGLASANG
Footing/Foundation/Slab 2/26/2020 Approved ANSON MAGLASANG
PLUMBING-Rough 2/26/2020 Partial Approval ANSON MAGLASANG
BUILDING-Rough-Frame 3/3/2020 Approved ANSON MAGLASANG
ELECTRICAL-Rough 3/3/2020 Approved ANSON MAGLASANG
Green Building Rough 3/3/2020 Approved ANSON MAGLASANG
Insulation 3/3/2020 Approved ANSON MAGLASANG
Interior/Exterior Lathing 3/3/2020 Partial Approval ANSON MAGLASANG
METHANE-Rough 3/3/2020 Approved ANSON MAGLASANG
Drywall Nailing 3/6/2020 Approved ANSON MAGLASANG
ELECTRICAL-Final 4/7/2020 Approved JOHN KLARIN
Final 4/7/2020 Conditional Approval JOHN KLARIN
Green Building Final 4/7/2020 Approved JOHN KLARIN
PLUMBING-Final 4/7/2020 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 4/7/2020 SGSOV Approved JOHN KLARIN
Smoke Detectors 4/7/2020 Approved JOHN KLARIN
Final 5/29/2020 OK to Issue CofO JOHN KLARIN