1203 W 25TH ST 90731
Certificate Information: 1203 W 25TH ST 90731
- Application / Permit
- 20016-40000-02428
- Plan Check / Job No.
- X20SP00493
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 2/07/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.8 Window and 2 door change-out (same size & type) for residential buildings. Dual glazing, labeled and certified by National Fenestration Rating Council (NFRC), is required for doors and windows replaced in all residential buildings, three stories or less, per Section 152(b) of Title 24. Kitchen remodel for residential buildings(no structural changes). Combined with mech/elec/plumb.
- Permit Issued
- Issued on 1/29/2020
- Issuing Office
- San Pedro
- Current Status
- Permit Finaled on 4/1/2020
Permit Application Status History
| No Progress | 1/28/2020 | GINA DELGADO |
| Issued | 1/29/2020 | LADBS |
| Permit Finaled | 4/1/2020 | ANDREW BEELI |
Permit Application Clearance Information
| Coastal Zone | Cleared | 1/29/2020 | JASON CHAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 2/3/2020 | Corrections Issued | ANDREW BEELI |
| ELECTRICAL-Rough | 3/3/2020 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Rough | 3/3/2020 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 3/6/2020 | Not Ready for Inspection | ANDREW BEELI |
| HVAC-Rough | 3/6/2020 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 3/6/2020 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 3/9/2020 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 3/9/2020 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Rough | 3/13/2020 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 3/20/2020 | Approved | ANDREW BEELI |
| ELECTRICAL-Final | 4/1/2020 | Approved | ANDREW BEELI |
| Final | 4/1/2020 | Permit Finaled | ANDREW BEELI |
| HVAC-Final | 4/1/2020 | Approved | ANDREW BEELI |
| PLUMBING-Final | 4/1/2020 | Approved | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 4/1/2020 | SGSOV Approved | ANDREW BEELI |