Supplemental to PCIS # 20016-30000-21372 to add a trellis to the rear of an (E) two-story SFD with attached garage. (N) BBQ area at rear of the dwelling with counters not exceeding 42" in height. (N) fireplace specs for 2nd floor fireplace.
Permit Issued
Issued on 1/3/2022
Issuing Office
Current Status
CofO Issued on 2/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2021 APPLICANT
Assigned to Plan Check Engineer 9/29/2021 JAHANSHAH POURHASSAN
Corrections Issued 9/29/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 11/4/2021 ALFREDO JARA
Applicant returned to address corrections 12/2/2021 MARJAN SHENASI
Building Plans Picked Up 12/7/2021 APPLICANT
Plan Check Approved 12/22/2021 JAHANSHAH POURHASSAN
Issued 1/3/2022 APPLICANT
CofO in Progress 2/10/2023 GERMAN RODRIGUEZ MENDOZA
Permit Finaled 2/10/2023 DANIEL ORRANTE
CofO Issued 2/10/2023 DANIEL ORRANTE
Permit Finaled 2/10/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/17/2021 PATRICK MISCHLICH
Watercourse Cleared 12/6/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 12/7/2021 HISASHI KOBAYAKAWA
Miscellaneous Cleared 12/10/2021 DANIEL CORONADO
ZA Case Cleared 12/10/2021 DANIEL CORONADO
ZA Case Cleared 12/10/2021 DANIEL CORONADO
GPI Written Notices Cleared 12/22/2021 JAHANSHAH POURHASSAN

Contact Information

Contractor J D Group Construction Company Inc; Lic. No.: 801797-B 1537 PONTIUS AVENUE SUITE B      LOS ANGELES, CA 90025
Engineer Shirley,, Peter Franklin; Lic. No.: C75050 4429 DAWES AVE      CULVER CITY, CA 90230

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/11/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 3/3/2022 Approved GERMAN RODRIGUEZ MENDOZA
Rough-Elec/Plmb/HVAC 3/7/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 12/21/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 12/22/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 2/7/2023 Approved GERMAN RODRIGUEZ MENDOZA
FLOOD-Proofing Certificate 2/7/2023 Approved GERMAN RODRIGUEZ MENDOZA
Final 2/7/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Green Building Final 2/7/2023 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 2/7/2023 Approved GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 2/7/2023 Approved GERMAN RODRIGUEZ MENDOZA