401 S HUDSON AVE 90020

Certificate Information: 401 S HUDSON AVE 90020

Application / Permit
20016-30002-07339
Plan Check / Job No.
B20WL03364
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental ref to pcis # 20016-30000-07339 for (N) covered patio and (N) uncovered deck off existing master bedroom. Per engineering design.
Permit Issued
Issued on 9/11/2020
Issuing Office
Current Status
CofO Issued on 10/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2020 APPLICANT
Assigned to Plan Check Engineer 8/11/2020 ALFREDO JARA
Corrections Issued 8/12/2020 ALFREDO JARA
Plan Check Approved 9/3/2020 ALFREDO JARA
Issued 9/11/2020 APPLICANT
Building Plans Picked Up 9/23/2020 APPLICANT
CofO in Progress 10/5/2022 JOSEPH MCGARRY
Permit Finaled 10/29/2022 DEROLD HAUFF
CofO Issued 10/29/2022 DEROLD HAUFF
Permit Finaled 10/29/2022 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 8/15/2020 SUKI GERSHENHORN
ZI Cleared 8/15/2020 SUKI GERSHENHORN
Grading Pre-Inspection Cleared 8/19/2020 PATRICK MISCHLICH
Eng Process Fee Ord 176,300 Cleared 8/25/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 8/25/2020 WALLIE JONG

Contact Information

Contractor Second Opinion A; Lic. No.: 752125-B 4243 BAKMAN AVENUE      STUDIO CITY, CA 91602
Engineer Perazzelli,, Joseph Ames; Lic. No.: C35270 183 GREENFIELD AVENUE      LOS ANGELES, CA 90049

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/8/2021 Partial Approval JOSEPH MCGARRY
METHANE-Barrier 3/8/2021 Approved JOSEPH MCGARRY
METHANE-Subgrade 3/8/2021 Approved JOSEPH MCGARRY
Deputy Reinf. Concrete 5/14/2021 Approved ALIZAH MAYAGOITIA
Deputy Reinf. Concrete 5/14/2021 Conditional Approval AMY COLIN
Structural Steel Frame 7/12/2021 Approved JOSEPH MCGARRY
Wood Frame 8/13/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 9/30/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 9/30/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 10/4/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 12/16/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 6/30/2022 Not Ready for Inspection ADAM ESCOTO
Final 6/30/2022 Corrections Issued ADAM ESCOTO
Green Building Final 6/30/2022 Not Ready for Inspection ADAM ESCOTO
Green Building Rough 6/30/2022 Not Ready for Inspection ADAM ESCOTO
METHANE-Final 6/30/2022 Not Ready for Inspection ADAM ESCOTO
METHANE-Rough 6/30/2022 Not Ready for Inspection ADAM ESCOTO
Smoke Detectors 6/30/2022 Not Ready for Inspection ADAM ESCOTO
BUILDING-Rough-Frame 9/30/2022 Approved JOSEPH MCGARRY
Final 9/30/2022 OK to Issue CofO JOSEPH MCGARRY
Green Building Final 9/30/2022 Approved JOSEPH MCGARRY
Green Building Rough 9/30/2022 Approved JOSEPH MCGARRY
METHANE-Final 9/30/2022 Approved JOSEPH MCGARRY
METHANE-Rough 9/30/2022 Approved JOSEPH MCGARRY
Smoke Detectors 9/30/2022 Approved JOSEPH MCGARRY