149 N CLIFFWOOD AVE 90049

Certificate Information: 149 N CLIFFWOOD AVE 90049

Application / Permit
20016-30001-14720
Plan Check / Job No.
B22WL00999
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO PERMIT NO. 20016-30000-14720 TO INCLUDE ADDITION TO REAR TRELLIS ATTACHED TO SINGLE FAMILY DWELLING PATIO WITH ROOF DECK ABOVE. See comments.
Permit Issued
Issued on 10/25/2022
Issuing Office
Current Status
Permit Finaled on 8/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2022 APPLICANT
Assigned to Plan Check Engineer 3/14/2022 SERGIO SILVA
Corrections Issued 4/13/2022 SERGIO SILVA
Applicant returned to address corrections 4/27/2022 SERGIO SILVA
Plan Check Approved 5/5/2022 SERGIO SILVA
Issued 10/25/2022 APPLICANT
Building Plans Picked Up 10/26/2022 APPLICANT
Permit Finaled 8/23/2023 ARAM AVEDISIAN

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Radziner,, Ronald Mark; Lic. No.: C22228 MARMOL RADZINER & ASSOCIATES   12210 NEBRASKA AVE    LOS ANGELES, CA 90025
Contractor Marmol Radziner An Architectural Corporation; Lic. No.: 734381-B 12210 NEBRASKA AVENUE      LOS ANGELES, CA 90025
Engineer Fischer,, Kurt Mark; Lic. No.: S5432 PO BOX 809      POWAY, CA 92074

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/31/2022 Corrections Issued DAVID FEILER
Pre-Inspection 11/14/2022 Approved JUAN VALENZUELA
Deputy Steel/Welding 12/21/2022 No Access for Inspection DAVID FEILER
Deputy Steel/Welding 12/22/2022 No Access for Inspection DAVID FEILER
Deputy Steel/Welding 1/20/2023 No Access for Inspection DAVID FEILER
ELECTRICAL-Rough 2/23/2023 Corrections Issued OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/23/2023 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Rough 2/28/2023 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 2/28/2023 Partial Approval KEVIN SARGSYAN
Structural Steel Frame 2/28/2023 Not Ready for Inspection KEVIN SARGSYAN
Wood Frame 2/28/2023 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 3/2/2023 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 3/2/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 3/3/2023 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 5/2/2023 Approved KEVIN SARGSYAN
Green Building Rough 5/2/2023 Approved KEVIN SARGSYAN
Drywall Nailing 7/19/2023 Approved KEVIN SARGSYAN
Final 7/19/2023 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 7/19/2023 Approved KEVIN SARGSYAN
Green Building Final 7/19/2023 Approved KEVIN SARGSYAN
Smoke Detectors 7/19/2023 Approved KEVIN SARGSYAN