586-588 W CYPRESS AVE 90065

Certificate Information: 586-588 W CYPRESS AVE 90065

Application / Permit
20016-30001-14164
Plan Check / Job No.
B23WL00131
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Supplemental ref to pcis # 20016-30000-14164, to change the ADU layout, revise structural drawings and change the engineer of record
Permit Issued
Issued on 8/10/2023
Issuing Office
Valley
Current Status
Permit Finaled on 1/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2023 APPLICANT
Assigned to Plan Check Engineer 2/9/2023 REZA HAGHIGHAT
Corrections Issued 2/12/2023 REZA HAGHIGHAT
Quality Review Completed 2/16/2023 KAVIAN REFAHI
Building Plans Picked Up 2/21/2023 APPLICANT
Plan Check Approved 3/31/2023 REZA HAGHIGHAT
Issued 8/10/2023 APPLICANT
Permit Finaled 1/5/2026 ALIZAH MAYAGOITIA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/27/2023 KIRK LINKLATER
Specific Plan Cleared 3/20/2023 NASHYA JENSEN

Contact Information

Contractor Builders Hub Renovation Inc; Lic. No.: 1063741-B 14622 VENTURA BLVD STE 102      SHERMAN OAKS, CA 91403
Engineer Boules,, George H; Lic. No.: C64144 29082 MADRID PL      CASTAIC, CA 91384

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/7/2023 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 9/15/2023 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 9/19/2023 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 9/19/2023 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 12/5/2023 Conditional Approval OSVALDO PARAMO
BUILDING-Rough-Frame 12/13/2023 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 12/13/2023 Corrections Issued OSVALDO PARAMO
Wood Frame 12/15/2023 Corrections Issued OSVALDO PARAMO
Wood Frame 1/4/2024 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 1/12/2024 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/22/2024 Approved OSVALDO PARAMO
Wood Frame 2/22/2024 Partial Inspection OSVALDO PARAMO
Insulation 4/1/2024 Not Ready for Inspection OSVALDO PARAMO
Insulation 7/22/2024 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 7/24/2024 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 7/24/2024 Corrections Issued OSVALDO PARAMO
HVAC-Rough 7/24/2024 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 7/24/2024 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 1/15/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 1/15/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/11/2025 Corrections Issued ALIZAH MAYAGOITIA
Drywall Nailing 6/3/2025 Not Ready for Inspection ANTHONY RAMOS
Drywall Nailing 6/18/2025 Approved JOSH MEISTER
Final 1/5/2026 Permit Finaled ALIZAH MAYAGOITIA
Smoke Detectors 1/5/2026 Approved ALIZAH MAYAGOITIA