2035 N DAVIES WAY 90046

Certificate Information: 2035 N DAVIES WAY 90046

Application / Permit
20016-30001-12248
Plan Check / Job No.
B20WL04085
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental permit to 20016-30000-12248 to add to existing SFD ** * 1 of 2 ***
Permit Issued
Issued on 6/8/2021
Issuing Office
Current Status
CofO Issued on 8/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 JASON JANGADA
Corrections Issued 10/27/2020 JASON JANGADA
Quality Review Completed 11/6/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/6/2021 JASON JANGADA
Applicant returned to address corrections 1/22/2021 JASON JANGADA
Applicant returned to address corrections 2/26/2021 JASON JANGADA
Building Plans Picked Up 3/1/2021 APPLICANT
Applicant returned to address corrections 3/9/2021 JASON JANGADA
Applicant returned to address corrections 3/17/2021 JASON JANGADA
Applicant returned to address corrections 4/15/2021 JASON JANGADA
Plan Check Approved 4/30/2021 JASON JANGADA
Issued 6/8/2021 APPLICANT
CofO in Progress 8/22/2024 RAUL BARAJAS
Permit Finaled 8/27/2024 RONALD MYRICK
CofO Issued 8/27/2024 RONALD MYRICK
Permit Finaled 8/27/2024 RONALD MYRICK

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/27/2020 JASON JANGADA
Sewer availability Cleared 12/16/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 12/18/2020 CECILIO NAVARRO
Distance to fire station Cleared 12/23/2020 JEREMY CARTER
Low Impact Development Cleared 4/22/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 4/28/2021 THAN WIN

Contact Information

Contractor Afco Construction; Lic. No.: 569722-B 6603 INDEPENDENCE AVENUE #D      CANOGA PARK, CA 91303
Engineer Shubeck,, Christopher Robert; Lic. No.: C66775 23705 VANOWEN ST 101      WEST HILLS, CA 91307
Engineer Sivushenka,, Mikita; Lic. No.: C87698 5525 CANOGA AVE APT 208      WOODLAND HILLS, CA 91367
Geologist Robinson,, Brian Anthony; Lic. No.: EG947 4930 GARDEN GROVE AVE      TARZANA, CA 91356

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/21/2021 Corrections Issued RICHARD STEINBACH
Footing/Foundation/Slab 7/27/2021 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 8/16/2021 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 8/16/2021 Partial Approval RAUL BARAJAS
Green Building Rough 8/16/2021 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 8/16/2021 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/20/2021 Corrections Issued RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 12/10/2021 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 12/29/2021 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 1/5/2022 Conditional Approval RAUL BARAJAS
Shower Pan 1/18/2022 Approved RAUL BARAJAS
ELECTRICAL-Rough 2/2/2022 Partial Approval RAUL BARAJAS
HVAC-Rough 2/2/2022 Partial Inspection RAUL BARAJAS
Interior/Exterior Lathing 2/2/2022 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 2/17/2022 Partial Approval RAUL BARAJAS
Shower Pan 2/17/2022 Approved RAUL BARAJAS
Interior/Exterior Lathing 3/4/2022 Approved RAUL BARAJAS
ELECTRICAL-Rough 3/17/2022 Approved RAUL BARAJAS
PLUMBING-Rough 3/17/2022 Approved RAUL BARAJAS
BUILDING-Rough-Frame 5/12/2022 Approved RAUL BARAJAS
Green Building Rough 5/12/2022 Approved RAUL BARAJAS
Insulation 5/12/2022 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 5/12/2022 Approved RAUL BARAJAS
Drywall Nailing 5/24/2022 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 5/24/2022 Partial Approval RYAN SALAZAR
Gas Test 6/3/2022 Partial Approval RAUL BARAJAS
Drywall Nailing 6/16/2022 Approved RAUL BARAJAS
ELECTRICAL-Rough 4/4/2023 Corrections Issued RAUL BARAJAS
ELECTRICAL-Final 8/18/2023 Not Ready for Inspection RAUL BARAJAS
HVAC-Final 8/18/2023 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Final 8/18/2023 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Final 9/7/2023 No Access for Inspection RAUL BARAJAS
Final 9/7/2023 No Access for Inspection RAUL BARAJAS
Footing/Foundation/Slab 9/7/2023 Approved RAUL BARAJAS
Green Building Final 9/7/2023 No Access for Inspection RAUL BARAJAS
PLUMBING-Final 9/7/2023 No Access for Inspection RAUL BARAJAS
Smoke Detectors 9/7/2023 No Access for Inspection RAUL BARAJAS
Final 9/19/2023 Corrections Issued RAUL BARAJAS
Green Building Final 9/19/2023 Not Ready for Inspection RAUL BARAJAS
Smoke Detectors 9/19/2023 Approved RAUL BARAJAS
ELECTRICAL-Final 10/27/2023 Approved RAUL BARAJAS
Final 10/27/2023 Corrections Issued RAUL BARAJAS
Gas Test 10/27/2023 Approved RAUL BARAJAS
HVAC-Final 10/27/2023 Approved RAUL BARAJAS
PLUMBING-Final 10/27/2023 Approved RAUL BARAJAS
Final 11/9/2023 Corrections Issued STUART CHAPMAN
Green Building Final 11/9/2023 Approved STUART CHAPMAN
Final 12/22/2023 Not Ready for Inspection RAUL BARAJAS
Final 8/19/2024 Corrections Issued RAUL BARAJAS
Final 8/21/2024 OK to Issue CofO RAUL BARAJAS