472 S HAMEL ROAD 90048
Certificate Information: 472 S HAMEL ROAD 90048
- Application / Permit
- 20016-30000-33566
- Plan Check / Job No.
- B20WL05668
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (e) garage to ADU per 6 CS 65852.2 (E)(I)(A)
- Permit Issued
- Issued on 12/7/2021
- Issuing Office
- Current Status
- CofO Issued on 2/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 1/21/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 1/26/2021 | TARIK SAOUD |
| Plan Check Approved | 10/28/2021 | FELIPE HERNANDEZ |
| Issued | 12/7/2021 | APPLICANT |
| Building Plans Picked Up | 5/24/2022 | APPLICANT |
| CofO in Progress | 2/12/2025 | MEL KHACHATOURIAN |
| Permit Finaled | 2/12/2025 | RICHARD STEINBACH |
| CofO Issued | 2/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2021 | JEANIE LAM |
| Sewer availability | Cleared | 2/2/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 3/23/2021 | JOHN CONNEALLY |
| Construction within easement | Cleared | 5/14/2021 | RIDWAN HARDY |
Contact Information
| Contractor | M Y Construction Inc; Lic. No.: 1036168-B | 10116 HILLGROVE DRIVE BEVERLY HILLS, CA 90210 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/5/2024 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 3/6/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 3/6/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 7/18/2024 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 7/29/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 10/4/2024 | Approved | MEL KHACHATOURIAN |
| Wood Frame | 10/4/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Wood Frame | 10/18/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 11/4/2024 | Approved | MEL KHACHATOURIAN |
| Wood Frame | 11/4/2024 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Approved | SEAN HAUPT |
| Insulation | 11/12/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 11/12/2024 | Corrections Issued | SEAN HAUPT |
| Special/Order Compliance | 11/12/2024 | Partial Inspection | BOBBY KEY |
| Drywall Nailing | 11/18/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 11/18/2024 | Approved | SEAN HAUPT |
| Final | 1/28/2025 | Corrections Issued | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2025 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 1/28/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 2/4/2025 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/4/2025 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 2/4/2025 | Approved | ARAM AVEDISIAN |
| Final | 2/11/2025 | OK to Issue CofO | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 2/11/2025 | SGSOV Approved | MEL KHACHATOURIAN |