472 S HAMEL ROAD 90048

Certificate Information: 472 S HAMEL ROAD 90048

Application / Permit
20016-30000-33566
Plan Check / Job No.
B20WL05668
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (e) garage to ADU per 6 CS 65852.2 (E)(I)(A)
Permit Issued
Issued on 12/7/2021
Issuing Office
Current Status
CofO Issued on 2/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 FELIPE HERNANDEZ
Corrections Issued 1/21/2021 FELIPE HERNANDEZ
Quality Review Completed 1/26/2021 TARIK SAOUD
Plan Check Approved 10/28/2021 FELIPE HERNANDEZ
Issued 12/7/2021 APPLICANT
Building Plans Picked Up 5/24/2022 APPLICANT
CofO in Progress 2/12/2025 MEL KHACHATOURIAN
Permit Finaled 2/12/2025 RICHARD STEINBACH
CofO Issued 2/12/2025 RICHARD STEINBACH
Permit Finaled 2/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/2/2021 JEANIE LAM
Sewer availability Cleared 2/2/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/3/2021 JEANIE LAM
Hydrant and Access approval Cleared 3/23/2021 JOHN CONNEALLY
Construction within easement Cleared 5/14/2021 RIDWAN HARDY

Contact Information

Contractor M Y Construction Inc; Lic. No.: 1036168-B 10116 HILLGROVE DRIVE      BEVERLY HILLS, CA 90210

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/5/2024 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 3/6/2024 Corrections Issued MEL KHACHATOURIAN
Footing/Foundation/Slab 3/6/2024 Not Ready for Inspection MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 7/18/2024 Partial Approval MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 7/29/2024 Approved MEL KHACHATOURIAN
METHANE-Rough 10/4/2024 Approved MEL KHACHATOURIAN
Wood Frame 10/4/2024 Corrections Issued MEL KHACHATOURIAN
Wood Frame 10/18/2024 Corrections Issued MEL KHACHATOURIAN
Verify Sprinkler Sign Off 11/4/2024 Approved MEL KHACHATOURIAN
Wood Frame 11/4/2024 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Approved SEAN HAUPT
Insulation 11/12/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 11/12/2024 Corrections Issued SEAN HAUPT
Special/Order Compliance 11/12/2024 Partial Inspection BOBBY KEY
Drywall Nailing 11/18/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 11/18/2024 Approved SEAN HAUPT
Final 1/28/2025 Corrections Issued MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Not Ready MEL KHACHATOURIAN
Smoke Detectors 1/28/2025 Not Ready for Inspection MEL KHACHATOURIAN
Final 2/4/2025 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 2/4/2025 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 2/4/2025 Approved ARAM AVEDISIAN
Final 2/11/2025 OK to Issue CofO MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 2/11/2025 SGSOV Approved MEL KHACHATOURIAN