1108 S GAYLEY AVE 90024

Certificate Information: 1108 S GAYLEY AVE 90024

Application / Permit
20016-30000-33285
Plan Check / Job No.
B20WL05624
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CORE & SHELL PERMIT ONLY FOR T.I. TO (E) RESTAURANT SPACE TO DEMO (E) INTERIOR STAIR, WALLS, MEZZANINE, CEILING, AND REPLACE (E) ROOF TOP UNITS IN (E) URM BLDG
Permit Issued
Issued on 9/24/2021
Issuing Office
Current Status
Permit Finaled on 1/13/2022

Permit Application Status History

Submitted 12/30/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 REZA HAGHIGHAT
Disabled Access Plans Picked Up 2/1/2021 APPLICANT
Corrections Issued 2/17/2021 REZA HAGHIGHAT
Quality Review Completed 2/19/2021 KAMRAN GHOTBI RAVANDI
Plan Check Approved 6/25/2021 REZA HAGHIGHAT
Issued 9/24/2021 APPLICANT
Building Plans Picked Up 12/21/2021 APPLICANT
Permit Finaled 1/12/2022 PAUL DAVIDSON

Permit Application Clearance Information

DAS Clearance Cleared 2/4/2021 REZA HAGHIGHAT
Eng Process Fee Ord 176,300 Cleared 3/10/2021 SAUL GARCIA
Sewer availability Cleared 3/10/2021 SAUL GARCIA
"D" conditions Cleared 3/11/2021 DYLAN SITTIG
Food Service Establishment Cleared 3/11/2021 PAWAN VERMA
Specific Plan Cleared 3/11/2021 DYLAN SITTIG
ZI Cleared 3/11/2021 DYLAN SITTIG
ZA Case Cleared 3/17/2021 LOUIS ORTEGA
City Hist. Cultural Monument Cleared 3/22/2021 LAMBERT GIESSINGER
Historic monument Cleared 3/22/2021 LAMBERT GIESSINGER
Food establishment approval Cleared 6/14/2021 LACDHS APPROVED

Contact Information

Architect Itaya,, Randolph M; Lic. No.: C27210 22607 W SARKIS COURT      SAUGUS, CA 91350
Contractor Tri - Quest Builders & Developers Inc; Lic. No.: 536909-B 4630 NORTHGATE BLVD STE #110      SACRAMENTO, CA 95834
Engineer Stewart,, Joseph Eugene; Lic. No.: S3065 4117 MEADOW LARK DR      CALABASAS, CA 91302

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Structural Steel Frame 12/16/2021 Not Ready for Inspection PAUL DAVIDSON
Light Gage Steel Frame 12/21/2021 Not Ready for Inspection PAUL DAVIDSON
Wood Frame 12/28/2021 Partial Inspection PAUL DAVIDSON
Light Gage Steel Frame 12/29/2021 Conditional Approval PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 1/7/2022 SGSOV Not Ready PAUL DAVIDSON
Smoke Detectors 1/7/2022 Approved PAUL DAVIDSON
Wood Frame 1/7/2022 Approved PAUL DAVIDSON
Final 1/12/2022 Permit Finaled PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 1/12/2022 SGSOV Approved PAUL DAVIDSON