881 N ALMA REAL DR 90272
Certificate Information: 881 N ALMA REAL DR 90272
- Application / Permit
- 20016-30000-32900
- Plan Check / Job No.
- B20WL05554
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Exterior alteration to (E) office building.
- Permit Issued
- Issued on 4/15/2022
- Issuing Office
- Current Status
- Permit Finaled on 11/1/2023
Permit Application Status History
| Submitted | 2/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2021 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 4/16/2021 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 4/16/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/2/2022 | MARJAN SHENASI |
| Building Plans Picked Up | 2/3/2022 | APPLICANT |
| Applicant returned to address corrections | 2/9/2022 | MARJAN SHENASI |
| Plan Check Approved | 2/18/2022 | MARJAN SHENASI |
| Issued | 4/15/2022 | APPLICANT |
| Permit Finaled | 10/31/2023 | GRANT WOODS |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/5/2021 | FREDDY GARCIA |
| Green Code | Cleared | 8/3/2021 | RICHARD GARCIA |
| DAS Clearance | Cleared | 9/1/2021 | EDDIE GARIN |
| Specific Plan | Cleared | 1/14/2022 | NOAH MCCOY |
Contact Information
| Architect | Ward,, Robert Tyson; Lic. No.: C14314 | 122 HART AVENUE SANTA MONICA, CA 90405 |
| Contractor | Ayala Development Inc; Lic. No.: 1006608-B | 13300 VICTORY BLVD SUITE 507 VALLEY GLEN, CA 91401 |
| Engineer | Perbix,, Todd William; Lic. No.: S3082 | 2004B CALIFORNIA AVE SW SEATTLE, WA 98116 |
| Engineer | Tsai,, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Interior/Exterior Lathing | 8/3/2022 | Partial Inspection | SORIN CIRSTOIU |
| Interior/Exterior Lathing | 8/11/2022 | Partial Approval | GRANT WOODS |
| Piling/Pier/Caisson | 9/9/2022 | Partial Inspection | SORIN CIRSTOIU |
| Deputy Grading | 9/12/2022 | Conditional Approval | SORIN CIRSTOIU |
| Deputy Grading | 9/13/2022 | Conditional Approval | SORIN CIRSTOIU |
| Excavation/Setback/Form/Re-Bar | 10/25/2022 | Partial Approval | GRANT WOODS |
| Footing/Foundation/Slab | 10/25/2022 | Partial Approval | GRANT WOODS |
| Reinforced Concrete Frame | 10/25/2022 | Partial Approval | GRANT WOODS |
| Masonry Wall/Backfill | 10/31/2022 | Partial Approval | DERRICK SPENCER |
| Special/Order Compliance | 12/1/2022 | Partial Inspection | SORIN CIRSTOIU |
| Special/Order Compliance | 3/9/2023 | Conditional Approval | SORIN CIRSTOIU |
| Excavation/Setback/Form/Re-Bar | 5/4/2023 | Not Ready for Inspection | GRANT WOODS |
| Masonry Wall/Backfill | 5/15/2023 | Partial Approval | GRANT WOODS |
| Final | 10/25/2023 | Conditional Approval | GRANT WOODS |
| Green Building Final | 10/25/2023 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 10/25/2023 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 10/25/2023 | Approved | GRANT WOODS |
| Final | 10/31/2023 | Permit Finaled | GRANT WOODS |