881 N ALMA REAL DR 90272

Certificate Information: 881 N ALMA REAL DR 90272

Application / Permit
20016-30000-32900
Plan Check / Job No.
B20WL05554
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Exterior alteration to (E) office building.
Permit Issued
Issued on 4/15/2022
Issuing Office
Current Status
Permit Finaled on 11/1/2023

Permit Application Status History

Submitted 2/11/2021 APPLICANT
Assigned to Plan Check Engineer 3/5/2021 VLADIMIR ARUTYUNYAN
Corrections Issued 4/16/2021 VLADIMIR ARUTYUNYAN
Quality Review Completed 4/16/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/2/2022 MARJAN SHENASI
Building Plans Picked Up 2/3/2022 APPLICANT
Applicant returned to address corrections 2/9/2022 MARJAN SHENASI
Plan Check Approved 2/18/2022 MARJAN SHENASI
Issued 4/15/2022 APPLICANT
Permit Finaled 10/31/2023 GRANT WOODS

Permit Application Clearance Information

Specific Plan Cleared 5/5/2021 FREDDY GARCIA
Green Code Cleared 8/3/2021 RICHARD GARCIA
DAS Clearance Cleared 9/1/2021 EDDIE GARIN
Specific Plan Cleared 1/14/2022 NOAH MCCOY

Contact Information

Architect Ward,, Robert Tyson; Lic. No.: C14314 122 HART AVENUE      SANTA MONICA, CA 90405
Contractor Ayala Development Inc; Lic. No.: 1006608-B 13300 VICTORY BLVD SUITE 507      VALLEY GLEN, CA 91401
Engineer Perbix,, Todd William; Lic. No.: S3082 2004B CALIFORNIA AVE SW      SEATTLE, WA 98116
Engineer Tsai,, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Interior/Exterior Lathing 8/3/2022 Partial Inspection SORIN CIRSTOIU
Interior/Exterior Lathing 8/11/2022 Partial Approval GRANT WOODS
Piling/Pier/Caisson 9/9/2022 Partial Inspection SORIN CIRSTOIU
Deputy Grading 9/12/2022 Conditional Approval SORIN CIRSTOIU
Deputy Grading 9/13/2022 Conditional Approval SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 10/25/2022 Partial Approval GRANT WOODS
Footing/Foundation/Slab 10/25/2022 Partial Approval GRANT WOODS
Reinforced Concrete Frame 10/25/2022 Partial Approval GRANT WOODS
Masonry Wall/Backfill 10/31/2022 Partial Approval DERRICK SPENCER
Special/Order Compliance 12/1/2022 Partial Inspection SORIN CIRSTOIU
Special/Order Compliance 3/9/2023 Conditional Approval SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 5/4/2023 Not Ready for Inspection GRANT WOODS
Masonry Wall/Backfill 5/15/2023 Partial Approval GRANT WOODS
Final 10/25/2023 Conditional Approval GRANT WOODS
Green Building Final 10/25/2023 Approved GRANT WOODS
SGSOV-Seismic Gas S/O Valve 10/25/2023 SGSOV Approved GRANT WOODS
Smoke Detectors 10/25/2023 Approved GRANT WOODS
Final 10/31/2023 Permit Finaled GRANT WOODS