2324 N GLOVER PL 90031
Certificate Information: 2324 N GLOVER PL 90031
- Application / Permit
- 20016-30000-32293
- Plan Check / Job No.
- B20WL05445
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADU conversion of (e) 1-story s.f.r. at rear of the property
- Permit Issued
- Issued on 6/7/2021
- Issuing Office
- Current Status
- CofO Issued on 2/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 12/28/2020 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 12/29/2020 | CHIHARU SUZUKI |
| Building Plans Picked Up | 1/4/2021 | APPLICANT |
| Applicant returned to address corrections | 4/27/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/4/2021 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 5/15/2021 | KAMRAN GHOTBI RAVANDI |
| Issued | 6/7/2021 | APPLICANT |
| CofO in Progress | 1/20/2022 | THOMAS LOGRASSO |
| Permit Finaled | 2/7/2022 | DEROLD HAUFF |
| CofO Issued | 2/7/2022 | DEROLD HAUFF |
| Permit Finaled | 2/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/15/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 1/21/2021 | CECILIO NAVARRO |
| ZI | Cleared | 2/19/2021 | LOUIS ORTEGA |
| Construction near power lines | Cleared | 4/13/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 4/19/2021 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 4/20/2021 | THAN WIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/22/2021 | No Access for Inspection | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 7/26/2021 | Corrections Issued | THOMAS LOGRASSO |
| Pre-Inspection | 7/29/2021 | Corrections Issued | THOMAS LOGRASSO |
| Special/Order Compliance | 7/29/2021 | Approved | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 7/30/2021 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/9/2021 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 9/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 9/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 9/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 9/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Underground Mechanical | 9/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 9/8/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 9/8/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/13/2021 | Corrections Issued | THOMAS LOGRASSO |
| MERV13>=Rough | 9/13/2021 | Partial Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/30/2021 | Conditional Approval | THOMAS LOGRASSO |
| MERV13>=Rough | 9/30/2021 | Approved | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 9/30/2021 | Conditional Approval | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 9/30/2021 | Approved | THOMAS LOGRASSO |
| Insulation | 10/5/2021 | Conditional Approval | THOMAS LOGRASSO |
| Drywall Nailing | 10/7/2021 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 10/7/2021 | Partial Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 10/14/2021 | Conditional Approval | THOMAS LOGRASSO |
| Shower Pan | 10/14/2021 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/16/2021 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 12/16/2021 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 12/16/2021 | Approved | THOMAS LOGRASSO |
| Final | 12/16/2021 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/16/2021 | Approved | THOMAS LOGRASSO |
| Gas Test | 12/16/2021 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 12/16/2021 | Approved | THOMAS LOGRASSO |
| Insulation | 12/16/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/16/2021 | Approved | THOMAS LOGRASSO |
| MERV13>=Final | 12/16/2021 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 12/16/2021 | Approved | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 12/16/2021 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/16/2021 | SGSOV Approved | THOMAS LOGRASSO |
| Shower Pan | 12/16/2021 | Approved | THOMAS LOGRASSO |
| Smoke Detectors | 12/16/2021 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 12/22/2021 | Approved | THOMAS LOGRASSO |
| Final | 12/22/2021 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Final | 12/22/2021 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 12/22/2021 | Approved | THOMAS LOGRASSO |
| Final | 1/20/2022 | OK to Issue CofO | THOMAS LOGRASSO |
| Service/Power Release | 1/20/2022 | Approved | THOMAS LOGRASSO |