12318 W 18TH HELENA DR 90049
Certificate Information: 12318 W 18TH HELENA DR 90049
- Application / Permit
- 20016-30000-30869
- Plan Check / Job No.
- B20WL05236
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- pool bath & wood deck with trellis to be constructed on existing pile & grade beam foundation of fire damaged pool house
- Permit Issued
- Issued on 12/28/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | SERGIO SILVA |
| Corrections Issued | 1/6/2021 | SERGIO SILVA |
| Quality Review Completed | 1/14/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/5/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 8/18/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 10/28/2021 | SERGIO SILVA |
| Plan Check Approved | 12/9/2021 | SERGIO SILVA |
| Issued | 12/28/2021 | APPLICANT |
| Building Plans Picked Up | 1/5/2022 | APPLICANT |
| CofO in Progress | 2/5/2025 | JESUS RODRIGUEZ |
| CofO Issued | 2/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 7/27/2021 | DINAH GARIN |
| Sewer availability | Cleared | 7/27/2021 | DINAH GARIN |
| Trees in Parkway | Cleared | 7/28/2021 | JOHN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 10/28/2021 | SERGIO SILVA |
| Green Code | Cleared | 10/28/2021 | SERGIO SILVA |
| Hydrant and Access approval | Cleared | 11/5/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 11/10/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/30/2021 | SAUL GARCIA |
Contact Information
| Architect | Leese,, Robert Frank; Lic. No.: C9073 | 2225 E ORANGE GROVE BLVD PASADENA, CA 91104 |
| Contractor | Nolan M S & Associates Inc; Lic. No.: 451294-B | 17140 OSBORNE STREET NORTHRIDGE, CA 91325 |
| Engineer | Howe,, Carl William; Lic. No.: C44773 | 4358 SEPULVEDA BLVD CULVER CITY, CA 90230 |
| Engineer | Schmahl,, Lawrence Joseph; Lic. No.: L5748 | 11209 HOWARD STREET WHITTIER, CA 90606 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/22/2022 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 7/25/2022 | Conditional Approval | KEVIN SARGSYAN |
| Reinforced Masonry Frame | 8/2/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 8/8/2022 | Conditional Approval | KEVIN SARGSYAN |
| Reinforced Masonry Frame | 8/8/2022 | Approved | JOHN KIDWELL |
| Deputy Reinf. Masonry | 8/9/2022 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 9/22/2022 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | No Access for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/26/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 4/26/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/26/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/11/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/11/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 5/11/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/11/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 5/11/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/25/2023 | Approved | OGANES TARAKHCHYAN |
| Insulation | 6/2/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 6/15/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/15/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 12/9/2024 | Approved | JESUS RODRIGUEZ |
| Final | 12/9/2024 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 12/9/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 12/9/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 12/9/2024 | Approved | JESUS RODRIGUEZ |
| Final | 2/3/2025 | OK to Issue CofO | JESUS RODRIGUEZ |