101 N PACIFIC AVE 90731
Certificate Information: 101 N PACIFIC AVE 90731
- Application / Permit
- 20016-30000-30659
- Plan Check / Job No.
- B20WL05200
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- change of use from auto body shop to retail store.
- Permit Issued
- Issued on 4/30/2021
- Issuing Office
- Current Status
- CofO Issued on 7/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | TARIK SAOUD |
| Corrections Issued | 1/12/2021 | TARIK SAOUD |
| Quality Review Completed | 1/20/2021 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 1/21/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 1/29/2021 | APPLICANT |
| Plan Check Approved | 3/18/2021 | TARIK SAOUD |
| Issued | 4/30/2021 | APPLICANT |
| CofO in Progress | 6/20/2023 | AMANUEL BERHE |
| CofO in Progress | 6/20/2023 | AMANUEL BERHE |
| CofO Issued | 7/21/2023 | DAVID TSAU |
| Permit Finaled | 7/21/2023 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 2/1/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2021 | ERIK BEASLEY |
| Redevelopment Project Area | Cleared | 2/22/2021 | DAVID URITA |
| Encroachment in public way | Cleared | 2/23/2021 | CHINH DINH |
| ZI | Cleared | 2/23/2021 | JEANALEE OBERGFELL |
| DAS Clearance | Cleared | 3/4/2021 | TARIK SAOUD |
Contact Information
| Architect | Verdugo,, Emilio Amado; Lic. No.: C33263 | 4324 GRANDVIEW BLVD LOS ANGELES, CA 90066 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/13/2021 | Corrections Issued | JOEY BUCHANAN |
| Footing/Foundation/Slab | 2/4/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 2/4/2022 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 3/4/2022 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 3/14/2022 | Conditional Approval | JOEY BUCHANAN |
| Insulation | 3/22/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 7/26/2022 | No Access for Inspection | JOEY BUCHANAN |
| Smoke Detectors | 7/26/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 1/26/2023 | Corrections Issued | AMANUEL BERHE |
| Wood Frame | 2/23/2023 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 3/16/2023 | Approved | JOEY BUCHANAN |
| Final | 5/18/2023 | Partial Approval | AMANUEL BERHE |
| Final | 6/13/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Final | 6/20/2023 | OK to Issue CofO | AMANUEL BERHE |