2328 S GREENFIELD AVE 90064
Certificate Information: 2328 S GREENFIELD AVE 90064
- Application / Permit
- 20016-30000-30638
- Plan Check / Job No.
- B20WL05192
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert a detached garage into an ADU
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Current Status
- CofO Issued on 1/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2020 | RICHARD GARCIA |
| Corrections Issued | 12/6/2020 | RICHARD GARCIA |
| Applicant returned to address corrections | 2/25/2021 | RICHARD GARCIA |
| Building Plans Picked Up | 2/25/2021 | APPLICANT |
| Applicant returned to address corrections | 3/4/2021 | RICHARD GARCIA |
| Plan Check Approved | 5/18/2021 | RICHARD GARCIA |
| Issued | 5/24/2021 | APPLICANT |
| CofO in Progress | 1/18/2022 | KEVIN SARGSYAN |
| Permit Finaled | 1/28/2022 | KENNETH NAGLE |
| CofO Issued | 1/28/2022 | KENNETH NAGLE |
| Permit Finaled | 1/28/2022 | KENNETH NAGLE |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/22/2020 | DYLAN SITTIG |
| Specific Plan | Cleared | 12/22/2020 | LAUREN PADICK |
| ZI | Cleared | 12/22/2020 | DYLAN SITTIG |
| ZI | Cleared | 12/22/2020 | LAUREN PADICK |
| Address approval | Cleared | 1/11/2021 | YEGANEH SADEGHI |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2021 | YEGANEH SADEGHI |
| Sewer availability | Cleared | 1/11/2021 | CHINH DINH |
| Grading Pre-Inspection | Cleared | 1/12/2021 | BARTON HOLMES |
| Specific Plan | Cleared | 3/12/2021 | EILEEN HUNT |
| Hydrant and Access approval | Cleared | 4/25/2021 | ROBERT DUFF |
Contact Information
| Architect | Madla,, Anne M; Lic. No.: C28087 | 3234 ETTRICK STREET LOS ANGELES, CA 90027 |
| Contractor | Owner-Builder | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/7/2021 | Partial Inspection | KEVIN SARGSYAN |
| Pre-Inspection | 6/11/2021 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Inspection | 7/8/2021 | Partial Inspection | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 9/2/2021 | Conditional Approval | MORRIS JACKSON |
| Footing/Foundation/Slab | 9/3/2021 | Partial Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 9/15/2021 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/16/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/30/2021 | Corrections Issued | KEVIN SARGSYAN |
| Sewer | 9/30/2021 | Corrections Issued | KEVIN SARGSYAN |
| Sewer | 10/1/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/7/2021 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/7/2021 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/13/2021 | No Access for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 10/13/2021 | No Access for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/14/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/14/2021 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/18/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/18/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/20/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 10/25/2021 | No Access for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/26/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 11/4/2021 | No Access for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 11/4/2021 | No Access for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 11/9/2021 | Partial Approval | KEVIN SARGSYAN |
| Green Building Rough | 11/9/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 11/9/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 11/9/2021 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 11/12/2021 | Partial Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 11/17/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2021 | Approved | KEVIN SARGSYAN |
| Insulation | 11/17/2021 | Approved | KEVIN SARGSYAN |
| Wood Frame | 11/17/2021 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 11/23/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/23/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/1/2021 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 12/1/2021 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/7/2021 | Approved | KEVIN SARGSYAN |
| Shower Pan | 12/7/2021 | Approved | KEVIN SARGSYAN |
| Final | 12/30/2021 | No Access for Inspection | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 12/30/2021 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 12/30/2021 | No Access for Inspection | KEVIN SARGSYAN |
| Final | 1/5/2022 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 1/5/2022 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 1/5/2022 | Approved | KEVIN SARGSYAN |
| Final | 1/7/2022 | Corrections Issued | KEVIN SARGSYAN |
| Final | 1/18/2022 | OK to Issue CofO | KEVIN SARGSYAN |