7509 S NAYLOR AVE 90045

Certificate Information: 7509 S NAYLOR AVE 90045

Application / Permit
20016-30000-30539
Plan Check / Job No.
B20WL05151
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE INTO AN ADU
Permit Issued
Issued on 5/15/2021
Issuing Office
Current Status
CofO Issued on 5/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/24/2020 APPLICANT
Assigned to Plan Check Engineer 12/1/2020 RICHARD GARCIA
Corrections Issued 12/5/2020 RICHARD GARCIA
Building Plans Picked Up 12/30/2020 APPLICANT
Applicant returned to address corrections 4/13/2021 FELIPE HERNANDEZ
Plan Check Approved 5/2/2021 FELIPE HERNANDEZ
Issued 5/15/2021 APPLICANT
CofO in Progress 5/24/2022 MARIAN PODPORA
Permit Finaled 5/24/2022 BRUCE TODD
CofO Issued 5/24/2022 BRUCE TODD
Permit Finaled 5/24/2022 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 2/22/2021 SAUL GARCIA
Sewer availability Cleared 2/22/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/23/2021 DINAH GARIN
ZI Cleared 2/23/2021 LOUIS ORTEGA
Specific Plan Cleared 3/10/2021 FREDDY GARCIA
Specific Plan Cleared 3/15/2021 LOUIS ORTEGA
ZI Cleared 3/15/2021 LOUIS ORTEGA
Grading Pre-Inspection Cleared 3/25/2021 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,
Engineer Ramos,, Yosimar; Lic. No.: C89832 1081 W ARROW HWY 2      AZUSA, CA 91702

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/21/2021 Approved MARIAN PODPORA
Footing/Foundation/Slab 12/22/2021 Partial Approval MARIAN PODPORA
ELECTRICAL-Rough 1/21/2022 Corrections Issued MARIAN PODPORA
PLUMBING-Rough 1/21/2022 Corrections Issued MARIAN PODPORA
ELECTRICAL-Rough 1/26/2022 Not Ready for Inspection MARIAN PODPORA
PLUMBING-Rough 1/26/2022 Approved MARIAN PODPORA
ELECTRICAL-Rough 2/1/2022 Approved MARIAN PODPORA
BUILDING-Rough-Frame 3/1/2022 Not Ready for Inspection MARIAN PODPORA
HVAC-Rough 3/1/2022 Corrections Issued MARIAN PODPORA
Insulation 3/1/2022 Approved MARIAN PODPORA
BUILDING-Rough-Frame 3/15/2022 Approved MARIAN PODPORA
HVAC-Rough 3/15/2022 Approved MARIAN PODPORA
Drywall Nailing 3/23/2022 Approved MARIAN PODPORA
Interior/Exterior Lathing 3/23/2022 Partial Approval MARIAN PODPORA
Footing/Foundation/Slab 4/8/2022 Partial Approval MARIAN PODPORA
Interior/Exterior Lathing 4/8/2022 Partial Approval MARIAN PODPORA
ELECTRICAL-Final 5/13/2022 Approved MARIAN PODPORA
HVAC-Final 5/13/2022 Approved MARIAN PODPORA
PLUMBING-Final 5/13/2022 Corrections Issued MARIAN PODPORA
Gas Test 5/19/2022 Approved MARIAN PODPORA
PLUMBING-Final 5/19/2022 Approved MARIAN PODPORA
Final 5/24/2022 Conditional Approval MARIAN PODPORA
SGSOV-Seismic Gas S/O Valve 5/24/2022 SGSOV Approved MARIAN PODPORA
Smoke Detectors 5/24/2022 Approved MARIAN PODPORA