7794-7796 W SKYHILL DR 90068

Certificate Information: 7794-7796 W SKYHILL DR 90068

Application / Permit
20016-30000-30241
Plan Check / Job No.
B20WL05085
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERSION OF (E) ATTACHED GARAGE AND (E) SECOND FLOOR MASTER SUITE TO ADU (Per CA Govt. Code 65852.2(e)(1)(A))
Permit Issued
Issued on 10/26/2021
Issuing Office
Current Status
CofO Issued on 4/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 MANUEL GARCIA
Corrections Issued 11/25/2020 MANUEL GARCIA
Building Plans Picked Up 12/7/2020 APPLICANT
Applicant returned to address corrections 4/27/2021 MARJAN SHENASI
Plan Check Approved 6/18/2021 MARJAN SHENASI
Issued 10/26/2021 APPLICANT
CofO in Progress 2/14/2022 BRIAN SULLIVAN
CofO in Progress 2/15/2022 BRIAN SULLIVAN
CofO Issued 4/19/2022 DEROLD HAUFF
Permit Finaled 4/19/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/26/2021 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 1/26/2021 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 1/26/2021 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 1/26/2021 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 1/26/2021 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 1/26/2021 LEE GUILBEAUX
Miscellaneous Cleared 1/26/2021 LEE GUILBEAUX
Sewer availability Cleared 1/26/2021 LEE GUILBEAUX
Low Impact Development Cleared 3/16/2021 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 3/18/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 3/18/2021 GABRIEL ROBLES
Specific Plan Cleared 4/16/2021 OLGA AYALA
ZI Cleared 4/16/2021 OLGA AYALA
Grading Pre-Inspection Cleared 4/28/2021 MANUEL GARCIA
Hydrant and Access approval Cleared 6/9/2021 JOHN CONNEALLY

Contact Information

Contractor United Builders & Development Inc; Lic. No.: 1066908-B 25350 MAGIC MOUNTAIN PARKWAY   STE #300    VALENCIA, CA 91355

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/8/2021 Corrections Issued BRIAN SULLIVAN
Sewer 11/8/2021 Not Ready for Inspection BRIAN SULLIVAN
Underground Mechanical 11/8/2021 Partial Approval BRIAN SULLIVAN
Deputy Drilled-In Anchors 11/9/2021 Conditional Approval BRIAN SULLIVAN
Footing/Foundation/Slab 11/12/2021 Approved RAUL BARAJAS
Deputy Drilled-In Anchors 11/15/2021 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 12/6/2021 Not Ready for Inspection BRIAN SULLIVAN
Rough-Elec/Plmb/HVAC 12/6/2021 Corrections Issued BRIAN SULLIVAN
Sewer 12/6/2021 Approved BRIAN SULLIVAN
Deputy Drilled-In Anchors 12/7/2021 Conditional Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 12/10/2021 Approved BRIAN SULLIVAN
Rough-Elec/Plmb/HVAC 12/10/2021 Approved BRIAN SULLIVAN
Underground Mechanical 12/10/2021 Approved BRIAN SULLIVAN
Insulation 12/17/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 12/17/2021 Approved BRIAN SULLIVAN
Drywall Nailing 12/22/2021 Approved BRIAN SULLIVAN
Final 2/9/2022 Corrections Issued BRIAN SULLIVAN
Gas Test 2/9/2022 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 2/9/2022 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 2/9/2022 Not Required BRIAN SULLIVAN
Smoke Detectors 2/9/2022 Corrections Issued BRIAN SULLIVAN
Final 2/14/2022 OK to Issue CofO BRIAN SULLIVAN
Gas Test 2/14/2022 Approved BRIAN SULLIVAN
Service/Power Release 2/14/2022 Approved BRIAN SULLIVAN
Smoke Detectors 2/14/2022 Approved BRIAN SULLIVAN
Final 2/15/2022 OK to Issue CofO BRIAN SULLIVAN
Gas Test 2/15/2022 Approved BRIAN SULLIVAN
Smoke Detectors 2/15/2022 Approved BRIAN SULLIVAN