2304 W PASEO DEL MAR 90732
Certificate Information: 2304 W PASEO DEL MAR 90732
- Application / Permit
- 20016-30000-30042
- Plan Check / Job No.
- B20WL05035
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR AND EXTERIOR REMODEL TO (E) SFD. PER ENGINEER'S CALCS.
- Permit Issued
- Issued on 7/14/2021
- Issuing Office
- Current Status
- Permit Finaled on 10/20/2021
Permit Application Status History
| Submitted | 11/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | MANUEL GARCIA |
| Corrections Issued | 11/25/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 1/28/2021 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 2/9/2021 | RICHARD GARCIA |
| Building Plans Picked Up | 2/9/2021 | APPLICANT |
| Plan Check Approved | 3/26/2021 | ALFREDO JARA |
| Issued | 7/14/2021 | APPLICANT |
| Permit Finaled | 10/20/2021 | ANDREW BEELI |
Permit Application Clearance Information
| ZA Case | Cleared | 12/24/2020 | RICHARD REASER |
| Coastal Zone | Cleared | 1/4/2021 | RICHARD REASER |
| Specific Plan | Cleared | 1/4/2021 | JEANALEE OBERGFELL |
| ZI | Cleared | 1/4/2021 | JEANALEE OBERGFELL |
| Grading Pre-Inspection | Cleared | 3/26/2021 | RICHARD GARCIA |
Contact Information
| Contractor | Primary Construction & Development Inc; Lic. No.: 1035793-B | 3925 CHEVY CHASE DR LA CANADA FLINTRIDGE, CA 91011 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/23/2021 | Conditional Approval | PAUL BECKER |
| BUILDING-Rough-Frame | 8/2/2021 | Corrections Issued | ANDREW BEELI |
| BUILDING-Rough-Frame | 8/9/2021 | Approved | ANDREW BEELI |
| Insulation | 8/12/2021 | Approved | ANDREW BEELI |
| Drywall Nailing | 8/19/2021 | Approved | ANDREW BEELI |
| Interior/Exterior Lathing | 8/24/2021 | Corrections Issued | ANDREW BEELI |
| ELECTRICAL-Final | 10/18/2021 | Approved | ANDREW BEELI |
| Final | 10/18/2021 | Corrections Issued | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 10/18/2021 | SGSOV Approved | ANDREW BEELI |
| Smoke Detectors | 10/18/2021 | Approved | ANDREW BEELI |
| Final | 10/20/2021 | Permit Finaled | ANDREW BEELI |