2219 S LONGWOOD AVE 90016

Certificate Information: 2219 S LONGWOOD AVE 90016

Application / Permit
20016-30000-29747
Plan Check / Job No.
B20WL05016
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of garage & storage to ADU per CA GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 8/30/2021
Issuing Office
Current Status
CofO Issued on 6/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/23/2020 APPLICANT
Assigned to Plan Check Engineer 12/1/2020 RICHARD GARCIA
Corrections Issued 12/5/2020 RICHARD GARCIA
Building Plans Picked Up 12/24/2020 APPLICANT
Applicant returned to address corrections 6/5/2021 JAHANSHAH POURHASSAN
Plan Check Approved 6/23/2021 JAHANSHAH POURHASSAN
Issued 8/30/2021 APPLICANT
CofO in Progress 6/3/2022 STUART CHAPMAN
Permit Finaled 6/30/2022 DEROLD HAUFF
CofO Issued 6/30/2022 DEROLD HAUFF
Permit Finaled 6/30/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/11/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 3/11/2021 CECILIO NAVARRO
Sewer availability Cleared 3/11/2021 CECILIO NAVARRO
ZI Cleared 4/5/2021 MINDY NGUYEN
ZI Cleared 4/5/2021 MINDY NGUYEN
Hydrant and Access approval Cleared 6/1/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/5/2021 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 10/5/2021 Approved STUART CHAPMAN
PLUMBING-Rough 10/5/2021 Approved STUART CHAPMAN
Deputy Drilled-In Anchors 10/6/2021 Conditional Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Partial Approval STUART CHAPMAN
MERV13>=Rough 10/13/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 10/15/2021 Approved STUART CHAPMAN
Special/Order Compliance 10/15/2021 Approved HECTOR ALIKHAN
ELECTRICAL-Rough 10/18/2021 Approved STUART CHAPMAN
Insulation 10/19/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 10/20/2021 Approved STUART CHAPMAN
Drywall Nailing 10/27/2021 Approved MASHEL JONGERT
Underground Mechanical 11/3/2021 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 3/31/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 3/31/2022 Approved STUART CHAPMAN
Final 3/31/2022 Corrections Issued STUART CHAPMAN
MERV13>=Final 3/31/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/31/2022 SGSOV Approved STUART CHAPMAN
Smoke Detectors 3/31/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 5/6/2022 Approved STUART CHAPMAN
Final 5/6/2022 Corrections Issued STUART CHAPMAN
HVAC-Final 5/6/2022 Approved STUART CHAPMAN
PLUMBING-Final 5/6/2022 Approved STUART CHAPMAN
Final 6/3/2022 OK to Issue CofO STUART CHAPMAN
Service/Power Release 6/3/2022 Approved STUART CHAPMAN