7222 N CANOGA AVE 91303

Certificate Information: 7222 N CANOGA AVE 91303

Application / Permit
20016-30000-29426
Plan Check / Job No.
B20WL04957
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
T.I. to (e) retail space and change of use to a restaurant (1080 sf) (Unit #7222) No change in parking.
Permit Issued
Issued on 6/18/2021
Issuing Office
Current Status
CofO Issued on 3/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2020 APPLICANT
Assigned to Plan Check Engineer 11/19/2020 REZA HAGHIGHAT
Corrections Issued 11/23/2020 REZA HAGHIGHAT
Quality Review Completed 12/4/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 12/8/2020 APPLICANT
Disabled Access Plans Picked Up 1/14/2021 APPLICANT
Plan Check Approved 5/5/2021 REZA HAGHIGHAT
Issued 6/18/2021 APPLICANT
CofO in Progress 2/17/2022 DANIEL VARNUM
Permit Finaled 3/1/2022 JEFFREY DURAN
CofO Issued 3/1/2022 JEFFREY DURAN
Permit Finaled 3/1/2022 JEFFREY DURAN

Permit Application Clearance Information

"Q" conditions Cleared 2/11/2021 MAXFIELD VERMY
ZA Case Cleared 2/11/2021 MAXFIELD VERMY
ZA Case Cleared 2/11/2021 MAXFIELD VERMY
ZA Case Cleared 2/11/2021 MAXFIELD VERMY
ZA Case Cleared 2/11/2021 MAXFIELD VERMY
City Hist. Cultural Monument Cleared 2/16/2021 MICAELA TORRES-GIL
Historic monument Cleared 2/16/2021 MICAELA TORRES-GIL
Food Service Establishment Cleared 2/26/2021 RAMESHBHAIR PATEL
Eng Process Fee Ord 176,300 Cleared 3/3/2021 GABRIEL ROBLES
Sewer availability Cleared 3/4/2021 GABRIEL ROBLES
DAS Clearance Cleared 4/8/2021 CHOI YAN
Food establishment approval Cleared 5/5/2021 LACDHS APPROVED

Contact Information

Contractor A - 1 Certified Electric Inc; Lic. No.: 863349-B 305 E STOCKER ST      GLENDALE, CA 91207

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/15/2021 Approved ANDREW DORSO
Light Gage Steel Frame 8/5/2021 Not Ready for Inspection CAMERON CHABAN
Light Gage Steel Frame 10/25/2021 Corrections Issued ANDREW DORSO
Drywall Nailing 11/2/2021 Approved ALAN NOVAK
T-Bar Ceiling 12/17/2021 Corrections Issued DANNY RODRIGUEZ
T-Bar Ceiling 1/20/2022 Partial Approval DANNY RODRIGUEZ
Final 2/9/2022 Partial Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 2/9/2022 SGSOV No Gas CAMERON CHABAN
Smoke Detectors 2/9/2022 Approved CAMERON CHABAN
Wood Frame 2/9/2022 Partial Inspection CAMERON CHABAN
Final 2/14/2022 Not Ready for Inspection CAMERON CHABAN
Wood Frame 2/14/2022 Approved CAMERON CHABAN
Final 2/16/2022 Partial Approval DANIEL VARNUM