5301 N BALBOA BLVD C2 91316

Certificate Information: 5301 N BALBOA BLVD C2 91316

Application / Permit
20016-30000-29139
Plan Check / Job No.
B20WL04926
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(35) Condo-Multi Family
Work Description
Remodeld (E) Condo unit # C2 , new flooring, no structural work Replace exterior window.
Permit Issued
Issued on 2/2/2021
Issuing Office
Current Status
Permit Finaled on 12/8/2021

Permit Application Status History

Submitted 11/10/2020 APPLICANT
Assigned to Plan Check Engineer 11/18/2020 MANUEL GARCIA
Corrections Issued 11/18/2020 MANUEL GARCIA
Plan Check Approved 12/4/2020 ALFREDO JARA
Building Plans Picked Up 12/30/2020 APPLICANT
Issued 2/2/2021 APPLICANT
Permit Finaled 12/6/2021 CAMERON CHABAN

Permit Application Clearance Information

ZA Case Cleared 11/23/2020 DENZEL HENDERSON
ZA Case Cleared 11/23/2020 DENZEL HENDERSON

Contact Information

Contractor Jencor Construction Inc; Lic. No.: 968170-B 19528 VENTURA BLVD 273      TARZANA, CA 91356

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/13/2021 Partial Inspection JEFFREY FULTON
Wood Frame 7/13/2021 Not Ready for Inspection JEFFREY FULTON
Insulation 8/5/2021 Not Ready for Inspection CAMERON CHABAN
Pre-Inspection 8/5/2021 Partial Inspection CAMERON CHABAN
Wood Frame 8/5/2021 Approved CAMERON CHABAN
Insulation 8/13/2021 Partial Approval DANNY RODRIGUEZ
Insulation 8/16/2021 Approved JOHN DODGE
Drywall Nailing 8/19/2021 Approved CAMERON CHABAN
Interior/Exterior Lathing 8/19/2021 Approved CAMERON CHABAN
Final 12/6/2021 Permit Finaled CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 12/6/2021 SGSOV Approved CAMERON CHABAN
Smoke Detectors 12/6/2021 Approved CAMERON CHABAN