1127 3/4 S BEDFORD ST 90035
Certificate Information: 1127 3/4 S BEDFORD ST 90035
- Application / Permit
- 20016-30000-28925
- Plan Check / Job No.
- B20WL04869
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 2ND STORY RECREATION ROOM INTO ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 8/27/2021
- Issuing Office
- Current Status
- Issued on 8/27/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2020 | RICHARD GARCIA |
| Corrections Issued | 11/21/2020 | RICHARD GARCIA |
| Building Plans Picked Up | 11/23/2020 | APPLICANT |
| Applicant returned to address corrections | 4/25/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 6/5/2021 | RICHARD GARCIA |
| Plan Check Approved | 7/12/2021 | SERGIO SILVA |
| Issued | 8/27/2021 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 12/8/2020 | RUBEN VASQUEZ |
| Address approval | Cleared | 1/6/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2021 | CELINA MORENO |
| Sewer availability | Cleared | 1/6/2021 | CELINA MORENO |
Contact Information
| Contractor | Michael N Soumekh; Lic. No.: 773770-B | 1140 SOUTH ALFRED STREET LOS ANGELES, CA 90035 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/10/2021 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 12/2/2021 | No Access for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 12/2/2021 | No Access for Inspection | EVAN COOPER |
| Final | 12/2/2021 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 12/2/2021 | No Access for Inspection | EVAN COOPER |
| METHANE-Final | 12/2/2021 | No Access for Inspection | EVAN COOPER |
| METHANE-Rough | 12/2/2021 | No Access for Inspection | EVAN COOPER |
| PLUMBING-Final | 12/2/2021 | No Access for Inspection | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/2/2021 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 12/2/2021 | No Access for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 12/7/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 12/7/2021 | Approved | EVAN COOPER |
| Final | 12/7/2021 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 12/7/2021 | Approved | EVAN COOPER |
| METHANE-Final | 12/7/2021 | Approved | EVAN COOPER |
| METHANE-Rough | 12/7/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 12/7/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/7/2021 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 12/7/2021 | Not Ready for Inspection | EVAN COOPER |
| Final | 2/28/2022 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 2/28/2022 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 2/28/2022 | Approved | EVAN COOPER |