5109 S OCEAN FRONT WALK 90292
Certificate Information: 5109 S OCEAN FRONT WALK 90292
- Application / Permit
- 20016-30000-28003
- Plan Check / Job No.
- B20WL04759
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- remodel and addition to (e) s.f.d. and (n) roof deck ***construction of a roof deck and dumbwaiter, exterior gates and fencing, and minor interior remodeling.***
- Permit Issued
- Issued on 4/22/2021
- Issuing Office
- Current Status
- CofO Issued on 3/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2020 | FELIPE HERNANDEZ |
| Corrections Issued | 11/16/2020 | FELIPE HERNANDEZ |
| Quality Review Completed | 11/19/2020 | TARIK SAOUD |
| Building Plans Picked Up | 11/23/2020 | APPLICANT |
| Plan Check Approved | 4/5/2021 | FELIPE HERNANDEZ |
| Issued | 4/22/2021 | APPLICANT |
| CofO in Progress | 3/1/2025 | HERBERT GIRON |
| CofO in Progress | 3/3/2025 | JEREMY GOSHORN |
| CofO in Progress | 3/3/2025 | JEREMY GOSHORN |
| Permit Finaled | 3/4/2025 | RICHARD STEINBACH |
| CofO Issued | 3/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/11/2020 | BINDU KANNAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2020 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 12/15/2020 | DENNIS BRAGIN |
| Construction within easement | Cleared | 1/4/2021 | WALTER RAMIREZ |
| Specific Plan | Cleared | 1/14/2021 | VALERIA CEJA |
| Coastal Zone | Cleared | 3/9/2021 | PABLO ESTRADA |
Contact Information
| Architect | Rios,, Mark William; Lic. No.: C15744 | 3101 W EXPOSITION PLACE LOS ANGELES, CA 90018 |
| Contractor | Dowbuilt Inc; Lic. No.: 948772-B | 4001 AURORA AVENUE NORTH SEATTLE, WA 98103 |
| Engineer | Parker,, Leo Augustine; Lic. No.: S2829 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/19/2022 | Partial Inspection | DAVID FEILER |
| Structural Steel Frame | 3/10/2022 | Partial Inspection | KENNETH NAGLE |
| Deputy Steel/Welding | 9/9/2022 | No Access for Inspection | DAVID FEILER |
| Deputy Steel/Welding | 10/5/2022 | No Access for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2022 | Partial Approval | KENNETH NAGLE |
| Pre-Inspection | 10/20/2022 | Partial Approval | KENNETH NAGLE |
| Deputy Drilled-In Anchors | 1/9/2023 | Conditional Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 1/23/2023 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 1/23/2023 | Not Ready for Inspection | HERBERT GIRON |
| Insulation | 1/23/2023 | Partial Approval | HERBERT GIRON |
| METHANE-Rough | 1/23/2023 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 1/23/2023 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2023 | Partial Approval | EVAN COOPER |
| Special/Order Compliance | 1/27/2023 | Corrections Issued | EVAN COOPER |
| Pre-Inspection | 3/20/2023 | Approved | EVAN COOPER |
| Pre-Inspection | 6/20/2023 | Approved | EVAN COOPER |
| Gas Test | 7/11/2023 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 7/11/2023 | Approved | EVAN COOPER |
| HVAC-Rough | 7/14/2023 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 8/3/2023 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 8/10/2023 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 8/10/2023 | Approved | EVAN COOPER |
| Green Building Rough | 8/10/2023 | Approved | EVAN COOPER |
| METHANE-Rough | 8/10/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 8/18/2023 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/24/2023 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 8/24/2023 | Approved | HERBERT GIRON |
| Insulation | 9/12/2023 | Partial Approval | TEMISTOCLES CAAL |
| Drywall Nailing | 11/16/2023 | Partial Approval | HERBERT GIRON |
| Insulation | 11/16/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 12/14/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 1/10/2024 | Partial Approval | HERBERT GIRON |
| Shower Pan | 1/10/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 1/16/2024 | Partial Approval | HERBERT GIRON |
| Pre-Inspection | 2/12/2024 | Partial Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 2/20/2024 | Partial Approval | HERBERT GIRON |
| Special/Order Compliance | 5/15/2024 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 6/5/2024 | Not Ready for Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 7/26/2024 | Partial Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 8/16/2024 | Approved | DANIEL VERA |
| ELECTRICAL-Rough | 8/22/2024 | Partial Inspection | HERBERT GIRON |
| Gas Test | 8/26/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 8/29/2024 | Partial Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 9/16/2024 | Approved | HERBERT GIRON |
| Service/Power Release | 9/20/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 10/4/2024 | No Access for Inspection | DAVID FEILER |
| ELECTRICAL-Final | 11/5/2024 | Corrections Issued | HERBERT GIRON |
| Service/Power Release | 11/20/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 11/22/2024 | Partial Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 12/2/2024 | Partial Approval | BOBBY KEY |
| Pre-Inspection | 12/4/2024 | Partial Inspection | HERBERT GIRON |
| Service/Power Release | 12/6/2024 | Approved | HERBERT GIRON |
| Special/Order Compliance | 12/31/2024 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Final | 1/8/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 1/15/2025 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/15/2025 | SGSOV Approved | HERBERT GIRON |
| ELECTRICAL-Final | 1/28/2025 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 1/28/2025 | Approved | HERBERT GIRON |
| HVAC-Final | 1/29/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 2/3/2025 | Corrections Issued | HERBERT GIRON |
| Final | 2/26/2025 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 2/26/2025 | Approved | HERBERT GIRON |
| HVAC-Final | 2/26/2025 | Approved | HERBERT GIRON |
| Smoke Detectors | 2/26/2025 | Approved | HERBERT GIRON |
| Final | 2/28/2025 | OK to Issue CofO | HERBERT GIRON |