5109 S OCEAN FRONT WALK 90292

Certificate Information: 5109 S OCEAN FRONT WALK 90292

Application / Permit
20016-30000-28003
Plan Check / Job No.
B20WL04759
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
remodel and addition to (e) s.f.d. and (n) roof deck ***construction of a roof deck and dumbwaiter, exterior gates and fencing, and minor interior remodeling.***
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
CofO Issued on 3/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2020 APPLICANT
Assigned to Plan Check Engineer 11/10/2020 FELIPE HERNANDEZ
Corrections Issued 11/16/2020 FELIPE HERNANDEZ
Quality Review Completed 11/19/2020 TARIK SAOUD
Building Plans Picked Up 11/23/2020 APPLICANT
Plan Check Approved 4/5/2021 FELIPE HERNANDEZ
Issued 4/22/2021 APPLICANT
CofO in Progress 3/1/2025 HERBERT GIRON
CofO in Progress 3/3/2025 JEREMY GOSHORN
CofO in Progress 3/3/2025 JEREMY GOSHORN
Permit Finaled 3/4/2025 RICHARD STEINBACH
CofO Issued 3/4/2025 RICHARD STEINBACH
Permit Finaled 3/4/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 12/11/2020 BINDU KANNAN
Eng Process Fee Ord 176,300 Cleared 12/15/2020 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 12/15/2020 DENNIS BRAGIN
Construction within easement Cleared 1/4/2021 WALTER RAMIREZ
Specific Plan Cleared 1/14/2021 VALERIA CEJA
Coastal Zone Cleared 3/9/2021 PABLO ESTRADA

Contact Information

Architect Rios,, Mark William; Lic. No.: C15744 3101 W EXPOSITION PLACE      LOS ANGELES, CA 90018
Contractor Dowbuilt Inc; Lic. No.: 948772-B 4001 AURORA AVENUE NORTH      SEATTLE, WA 98103
Engineer Parker,, Leo Augustine; Lic. No.: S2829 1927 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/19/2022 Partial Inspection DAVID FEILER
Structural Steel Frame 3/10/2022 Partial Inspection KENNETH NAGLE
Deputy Steel/Welding 9/9/2022 No Access for Inspection DAVID FEILER
Deputy Steel/Welding 10/5/2022 No Access for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/20/2022 Partial Approval KENNETH NAGLE
Pre-Inspection 10/20/2022 Partial Approval KENNETH NAGLE
Deputy Drilled-In Anchors 1/9/2023 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 1/23/2023 Partial Approval HERBERT GIRON
Green Building Rough 1/23/2023 Not Ready for Inspection HERBERT GIRON
Insulation 1/23/2023 Partial Approval HERBERT GIRON
METHANE-Rough 1/23/2023 Partial Approval HERBERT GIRON
PLUMBING-Rough 1/23/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Partial Approval EVAN COOPER
Special/Order Compliance 1/27/2023 Corrections Issued EVAN COOPER
Pre-Inspection 3/20/2023 Approved EVAN COOPER
Pre-Inspection 6/20/2023 Approved EVAN COOPER
Gas Test 7/11/2023 Partial Approval EVAN COOPER
PLUMBING-Rough 7/11/2023 Approved EVAN COOPER
HVAC-Rough 7/14/2023 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 8/3/2023 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 8/10/2023 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 8/10/2023 Approved EVAN COOPER
Green Building Rough 8/10/2023 Approved EVAN COOPER
METHANE-Rough 8/10/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 8/18/2023 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 8/24/2023 Approved HERBERT GIRON
Verify Sprinkler Sign Off 8/24/2023 Approved HERBERT GIRON
Insulation 9/12/2023 Partial Approval TEMISTOCLES CAAL
Drywall Nailing 11/16/2023 Partial Approval HERBERT GIRON
Insulation 11/16/2023 Approved HERBERT GIRON
Drywall Nailing 12/14/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 1/10/2024 Partial Approval HERBERT GIRON
Shower Pan 1/10/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 1/16/2024 Partial Approval HERBERT GIRON
Pre-Inspection 2/12/2024 Partial Inspection HERBERT GIRON
Interior/Exterior Lathing 2/20/2024 Partial Approval HERBERT GIRON
Special/Order Compliance 5/15/2024 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 6/5/2024 Not Ready for Inspection HERBERT GIRON
Interior/Exterior Lathing 7/26/2024 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 8/16/2024 Approved DANIEL VERA
ELECTRICAL-Rough 8/22/2024 Partial Inspection HERBERT GIRON
Gas Test 8/26/2024 Approved HERBERT GIRON
ELECTRICAL-Rough 8/29/2024 Partial Inspection HERBERT GIRON
Interior/Exterior Lathing 9/16/2024 Approved HERBERT GIRON
Service/Power Release 9/20/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 10/4/2024 No Access for Inspection DAVID FEILER
ELECTRICAL-Final 11/5/2024 Corrections Issued HERBERT GIRON
Service/Power Release 11/20/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 11/22/2024 Partial Inspection HERBERT GIRON
ELECTRICAL-Final 12/2/2024 Partial Approval BOBBY KEY
Pre-Inspection 12/4/2024 Partial Inspection HERBERT GIRON
Service/Power Release 12/6/2024 Approved HERBERT GIRON
Special/Order Compliance 12/31/2024 Partial Approval MICHAEL ALLEN
PLUMBING-Final 1/8/2025 Corrections Issued HERBERT GIRON
PLUMBING-Final 1/15/2025 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/15/2025 SGSOV Approved HERBERT GIRON
ELECTRICAL-Final 1/28/2025 Approved HERBERT GIRON
Interior/Exterior Lathing 1/28/2025 Approved HERBERT GIRON
HVAC-Final 1/29/2025 Corrections Issued HERBERT GIRON
HVAC-Final 2/3/2025 Corrections Issued HERBERT GIRON
Final 2/26/2025 Corrections Issued HERBERT GIRON
Green Building Final 2/26/2025 Approved HERBERT GIRON
HVAC-Final 2/26/2025 Approved HERBERT GIRON
Smoke Detectors 2/26/2025 Approved HERBERT GIRON
Final 2/28/2025 OK to Issue CofO HERBERT GIRON