6423 W HEDDING ST 90045
Certificate Information: 6423 W HEDDING ST 90045
- Application / Permit
- 20016-30000-27884
- Plan Check / Job No.
- B20WL04735
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (E) detached garage into an accessory dwelling unit with storage under GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 7/21/2021
- Issuing Office
- Current Status
- CofO Issued on 8/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2020 | JASON JANGADA |
| Corrections Issued | 11/11/2020 | JASON JANGADA |
| Building Plans Picked Up | 11/17/2020 | APPLICANT |
| Applicant returned to address corrections | 4/30/2021 | HOOMAN HAJIZADEH |
| Plan Check Approved | 4/30/2021 | HOOMAN HAJIZADEH |
| Plan Check Approved | 5/26/2021 | ALFREDO JARA |
| Issued | 7/21/2021 | APPLICANT |
| CofO in Progress | 8/7/2023 | HERBERT GIRON |
| Permit Finaled | 8/10/2023 | DANIEL ORRANTE |
| CofO Issued | 8/10/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/10/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2021 | DINAH GARIN |
| Sewer availability | Cleared | 1/13/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2021 | DINAH GARIN |
| Specific Plan | Cleared | 2/3/2021 | PEDRO AYALA |
| Hydrant and Access approval | Cleared | 2/12/2021 | KURT CORRAL |
| Construction near power lines | Cleared | 4/3/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/3/2021 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 4/16/2021 | KIRK LINKLATER |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/27/2021 | Approved | JOHN KAYON |
| Footing/Foundation/Slab | 10/29/2021 | Conditional Approval | RICHARD STEINBACH |
| Underground Mechanical | 12/21/2021 | Partial Approval | JOHN KAYON |
| Deputy Drilled-In Anchors | 12/29/2021 | Conditional Approval | BOBBY KEY |
| Deputy Wood Construction | 12/29/2021 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 1/10/2022 | Approved | JOHN KAYON |
| ELECTRICAL-Rough | 1/10/2022 | Corrections Issued | JOHN KAYON |
| Gas Test | 1/10/2022 | Approved | JOHN KAYON |
| Green Building Rough | 1/10/2022 | Approved | JOHN KAYON |
| METHANE-Rough | 1/10/2022 | Approved | JOHN KAYON |
| PLUMBING-Rough | 1/10/2022 | Approved | JOHN KAYON |
| Underground Mechanical | 1/10/2022 | Approved | JOHN KAYON |
| Insulation | 5/17/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/25/2022 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 5/31/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 1/20/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 1/24/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 2/13/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 2/17/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 2/17/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 2/17/2023 | Approved | HERBERT GIRON |
| Pre-Inspection | 4/7/2023 | Partial Inspection | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 6/23/2023 | SGSOV Not Ready | HERBERT GIRON |
| ELECTRICAL-Final | 6/28/2023 | Approved | HERBERT GIRON |
| Final | 6/28/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 6/28/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 6/28/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 6/28/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 6/28/2023 | Approved | HERBERT GIRON |
| Final | 8/7/2023 | OK to Issue CofO | HERBERT GIRON |
| Green Building Final | 8/7/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 8/7/2023 | Approved | HERBERT GIRON |