15353 W VOSE ST 91406
Certificate Information: 15353 W VOSE ST 91406
- Application / Permit
- 20016-30000-27869
- Plan Check / Job No.
- B20WL04730
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition to and conversion of (e) garage into an ADU.
- Permit Issued
- Issued on 6/1/2022
- Issuing Office
- Current Status
- CofO Issued on 1/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2020 | RICHARD GARCIA |
| Corrections Issued | 11/11/2020 | RICHARD GARCIA |
| Applicant returned to address corrections | 3/4/2021 | RICHARD GARCIA |
| Plan Check Approved | 5/6/2021 | RICHARD GARCIA |
| No Progress | 5/6/2021 | RICHARD GARCIA |
| Plan Check Approved | 5/6/2021 | RICHARD GARCIA |
| Issued | 6/1/2022 | APPLICANT |
| Building Plans Picked Up | 6/3/2022 | APPLICANT |
| CofO in Progress | 4/21/2023 | RYAN SALAZAR |
| CofO in Progress | 4/21/2023 | RYAN SALAZAR |
| CofO in Progress | 10/31/2023 | RYAN SALAZAR |
| No Progress | 12/27/2023 | ROBERT GOLD |
| CofO in Progress | 1/17/2024 | ROBERT GOLD |
| Permit Finaled | 1/23/2024 | RUBEN SALAS |
| CofO Issued | 1/23/2024 | RUBEN SALAS |
| Permit Finaled | 1/23/2024 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 2/4/2021 | DANIEL CORONADO |
| Address approval | Cleared | 3/19/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 3/19/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/23/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/19/2022 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 9/28/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/11/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/20/2022 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/17/2022 | Partial Approval | MICHAEL SMITH |
| Sewer | 12/27/2022 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/9/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 1/9/2023 | Approved | RYAN SALAZAR |
| Gas Test | 1/9/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 1/9/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/9/2023 | SGSOV Not Ready | RYAN SALAZAR |
| Insulation | 1/18/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 1/23/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/9/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 2/9/2023 | Approved | RYAN SALAZAR |
| Final | 4/12/2023 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 4/12/2023 | Approved | JOHN COLEMAN |
| Green Building Final | 4/12/2023 | Approved | JOHN COLEMAN |
| Green Building Rough | 4/12/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 4/12/2023 | SGSOV Approved | JOHN COLEMAN |
| Smoke Detectors | 4/12/2023 | Approved | JOHN COLEMAN |
| Wood Frame | 4/12/2023 | Approved | JOHN COLEMAN |
| Final | 4/20/2023 | Partial Inspection | RYAN SALAZAR |
| Special/Order Compliance | 4/25/2023 | Corrections Issued | RYAN SALAZAR |
| Final | 11/2/2023 | OK to Issue CofO | RYAN SALAZAR |