15353 W VOSE ST 91406

Certificate Information: 15353 W VOSE ST 91406

Application / Permit
20016-30000-27869
Plan Check / Job No.
B20WL04730
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to and conversion of (e) garage into an ADU.
Permit Issued
Issued on 6/1/2022
Issuing Office
Current Status
CofO Issued on 1/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2020 APPLICANT
Assigned to Plan Check Engineer 11/10/2020 RICHARD GARCIA
Corrections Issued 11/11/2020 RICHARD GARCIA
Applicant returned to address corrections 3/4/2021 RICHARD GARCIA
Plan Check Approved 5/6/2021 RICHARD GARCIA
No Progress 5/6/2021 RICHARD GARCIA
Plan Check Approved 5/6/2021 RICHARD GARCIA
Issued 6/1/2022 APPLICANT
Building Plans Picked Up 6/3/2022 APPLICANT
CofO in Progress 4/21/2023 RYAN SALAZAR
CofO in Progress 4/21/2023 RYAN SALAZAR
CofO in Progress 10/31/2023 RYAN SALAZAR
No Progress 12/27/2023 ROBERT GOLD
CofO in Progress 1/17/2024 ROBERT GOLD
Permit Finaled 1/23/2024 RUBEN SALAS
CofO Issued 1/23/2024 RUBEN SALAS
Permit Finaled 1/23/2024 RUBEN SALAS

Permit Application Clearance Information

ZI Cleared 2/4/2021 DANIEL CORONADO
Address approval Cleared 3/19/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 3/19/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/23/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/23/2021 JOHN TRIANTAFYLLOS

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/19/2022 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 9/28/2022 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 10/11/2022 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 10/20/2022 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 11/17/2022 Partial Approval MICHAEL SMITH
Sewer 12/27/2022 Approved RYAN SALAZAR
BUILDING-Rough-Frame 1/9/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 1/9/2023 Approved RYAN SALAZAR
Gas Test 1/9/2023 Approved RYAN SALAZAR
PLUMBING-Rough 1/9/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 1/9/2023 SGSOV Not Ready RYAN SALAZAR
Insulation 1/18/2023 Approved RYAN SALAZAR
Drywall Nailing 1/23/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 2/9/2023 Approved RYAN SALAZAR
Shower Pan 2/9/2023 Approved RYAN SALAZAR
Final 4/12/2023 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 4/12/2023 Approved JOHN COLEMAN
Green Building Final 4/12/2023 Approved JOHN COLEMAN
Green Building Rough 4/12/2023 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 4/12/2023 SGSOV Approved JOHN COLEMAN
Smoke Detectors 4/12/2023 Approved JOHN COLEMAN
Wood Frame 4/12/2023 Approved JOHN COLEMAN
Final 4/20/2023 Partial Inspection RYAN SALAZAR
Special/Order Compliance 4/25/2023 Corrections Issued RYAN SALAZAR
Final 11/2/2023 OK to Issue CofO RYAN SALAZAR