11361 W MONTANA AVE 90049
Certificate Information: 11361 W MONTANA AVE 90049
- Application / Permit
- 20016-30000-27782
- Plan Check / Job No.
- B20WL04721
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ADU
- Permit Issued
- Issued on 2/19/2021
- Issuing Office
- Current Status
- CofO Issued on 1/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2020 | RICHARD GARCIA |
| Corrections Issued | 11/7/2020 | RICHARD GARCIA |
| Applicant returned to address corrections | 1/12/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 1/28/2021 | MARJAN SHENASI |
| Plan Check Approved | 2/9/2021 | RICHARD GARCIA |
| Issued | 2/19/2021 | APPLICANT |
| Building Plans Picked Up | 2/26/2021 | APPLICANT |
| CofO in Progress | 1/14/2022 | CARLOS MATAMOROS |
| CofO in Progress | 1/14/2022 | CARLOS MATAMOROS |
| Permit Finaled | 1/18/2022 | DANIEL ORRANTE |
| CofO Issued | 1/18/2022 | DANIEL ORRANTE |
| Permit Finaled | 1/18/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 11/17/2020 | NOAH MCCOY |
| ZI | Cleared | 11/17/2020 | NOAH MCCOY |
| ZI | Cleared | 11/17/2020 | NOAH MCCOY |
| ZI | Cleared | 11/17/2020 | NOAH MCCOY |
| Address approval | Cleared | 11/18/2020 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2020 | SAUL GARCIA |
| Construction near power lines | Cleared | 12/8/2020 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 1/12/2021 | RICHARD GARCIA |
Contact Information
| Contractor | Karma Builders Inc; Lic. No.: 878865-B | 14440 MAGNOLIA BLVD SHERMAN OAKS, CA 91401 |
| Engineer | Lotfi,, Fariborz Frank; Lic. No.: C49359 | 1328 DUENDE LANE PACIFIC PALISADES, CA 90272 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/26/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/15/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 4/15/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 4/15/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| MERV13>=Rough | 4/15/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 4/15/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/23/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 4/23/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2021 | Approved | CARLOS MATAMOROS |
| Gas Test | 4/23/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 4/23/2021 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 4/23/2021 | Approved | CARLOS MATAMOROS |
| MERV13>=Rough | 4/23/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 4/23/2021 | Approved | CARLOS MATAMOROS |
| Insulation | 5/24/2021 | Corrections Issued | CARLOS MATAMOROS |
| Shower Pan | 5/24/2021 | Corrections Issued | CARLOS MATAMOROS |
| Insulation | 5/27/2021 | Approved | CARLOS MATAMOROS |
| Shower Pan | 5/27/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Drywall Nailing | 6/2/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 6/2/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Shower Pan | 6/2/2021 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 6/2/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 6/11/2021 | Partial Inspection | AMY COLIN |
| ELECTRICAL-Final | 10/13/2021 | Approved | CARLOS MATAMOROS |
| Final | 10/13/2021 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Final | 10/13/2021 | Corrections Issued | CARLOS MATAMOROS |
| MERV13>=Final | 10/13/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 10/13/2021 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 10/13/2021 | SGSOV Approved | CARLOS MATAMOROS |
| Service/Power Release | 10/13/2021 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 10/13/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 11/9/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 11/9/2021 | Approved | CARLOS MATAMOROS |
| Pre-Inspection | 11/9/2021 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 11/9/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 12/6/2021 | Approved | CARLOS MATAMOROS |
| Final | 12/6/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 12/6/2021 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Final | 12/6/2021 | Approved | CARLOS MATAMOROS |
| Final | 12/17/2021 | Partial Approval | CARLOS MATAMOROS |
| Final | 1/14/2022 | OK to Issue CofO | CARLOS MATAMOROS |