15240 W RAYNETA DR 91403

Certificate Information: 15240 W RAYNETA DR 91403

Application / Permit
20016-30000-27580
Plan Check / Job No.
B20WL04684
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior structural remodel of existing SFD, Converting study area into a bedroom. No new floor area
Permit Issued
Issued on 1/26/2021
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 9/14/2021

Permit Application Status History

Submitted 10/27/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 RICHARD GARCIA
Corrections Issued 10/31/2020 RICHARD GARCIA
Applicant returned to address corrections 12/9/2020 RICHARD GARCIA
Plan Check Approved 12/28/2020 RICHARD GARCIA
Issued 1/26/2021 APPLICANT
Building Plans Picked Up 1/26/2021 APPLICANT
Permit Finaled 9/14/2021 MISAEL ESPARZA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/30/2020 ADRIAN CASTRO
Sewer availability Cleared 11/30/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 12/28/2020 RICHARD GARCIA

Contact Information

Architect Kellen,, David; Lic. No.: C15684 2701 AIRPORT AVE 202      SANTA MONICA, CA 90405
Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/30/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 4/30/2021 Approved ARTHUR SARGSYAN
HVAC-Rough 4/30/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 4/30/2021 Approved ARTHUR SARGSYAN
Sewer 4/30/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 5/5/2021 Approved CHARLES POWELL
ELECTRICAL-Rough 5/5/2021 Approved CHARLES POWELL
Insulation 5/7/2021 Approved CHRISTOPHE COCHRAN
Pre-Inspection 5/7/2021 Approved CHRISTOPHE COCHRAN
Gas Test 5/11/2021 Approved CHARLES POWELL
Shower Pan 5/17/2021 Approved DANIEL ORRANTE
Drywall Nailing 5/28/2021 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 6/4/2021 Partial Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 6/18/2021 Approved ALAN MORELOS
ELECTRICAL-Final 9/10/2021 Approved CHRISTOPHER DELLEFIELD
Final 9/10/2021 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Final 9/10/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 9/10/2021 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 9/10/2021 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Smoke Detectors 9/10/2021 Approved CHRISTOPHER DELLEFIELD
Final 9/14/2021 Permit Finaled MISAEL ESPARZA
PLUMBING-Final 9/14/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/14/2021 SGSOV Approved MISAEL ESPARZA