4069 S LYCEUM AVE 90066

Certificate Information: 4069 S LYCEUM AVE 90066

Application / Permit
20016-30000-26958
Plan Check / Job No.
B20WL04610
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached garage to accessory dwelling unit per GCS 65852.2(e)(1)(A) and storage.
Permit Issued
Issued on 4/5/2021
Issuing Office
Current Status
CofO Issued on 9/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 JASON JANGADA
Corrections Issued 10/24/2020 JASON JANGADA
Applicant returned to address corrections 12/2/2020 JASON JANGADA
Plan Check Approved 2/27/2021 MANUEL GARCIA
Building Plans Picked Up 3/1/2021 APPLICANT
Issued 4/5/2021 APPLICANT
CofO in Progress 9/14/2021 ENRIQUE MIRELES
CofO Issued 9/21/2021 RONALD MYRICK
Permit Finaled 9/21/2021 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 11/10/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 11/10/2020 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 11/12/2020 HISASHI KOBAYAKAWA
Construction near power lines Cleared 1/10/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 1/22/2021 MATTHEW CRAIG

Contact Information

Architect Holz,, Michael B; Lic. No.: C28082 12548 EVERGLADE STREET      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/19/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 4/28/2021 Approved ENRIQUE MIRELES
Pre-Inspection 4/28/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 5/5/2021 Partial Approval ENRIQUE MIRELES
PLUMBING-Rough 5/5/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 5/13/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 5/13/2021 Approved ENRIQUE MIRELES
Sewer 5/13/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 5/21/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 5/21/2021 Approved ENRIQUE MIRELES
Insulation 5/21/2021 Approved ENRIQUE MIRELES
Drywall Nailing 5/26/2021 Approved ENRIQUE MIRELES
Insulation 5/26/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 6/8/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 6/8/2021 Approved ENRIQUE MIRELES
Final 6/8/2021 Corrections Issued ENRIQUE MIRELES
Green Building Final 6/8/2021 Approved ENRIQUE MIRELES
Green Building Rough 6/8/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 6/8/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 6/8/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 6/8/2021 Approved ENRIQUE MIRELES
Final 6/11/2021 Corrections Issued ENRIQUE MIRELES
Final 9/14/2021 OK to Issue CofO ENRIQUE MIRELES