742 N SUNNYHILL DR 90065

Certificate Information: 742 N SUNNYHILL DR 90065

Application / Permit
20016-30000-26808
Plan Check / Job No.
B20WL04588
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Structural remodel of (e) sfd. Interior and exterior remodeling. New bathroom at lower level. No additional floor area.
Permit Issued
Issued on 4/9/2021
Issuing Office
Current Status
Permit Finaled on 11/4/2022

Permit Application Status History

Submitted 10/21/2020 APPLICANT
Assigned to Plan Check Engineer 11/2/2020 RICHARD GARCIA
Corrections Issued 11/2/2020 RICHARD GARCIA
Building Plans Picked Up 11/5/2020 APPLICANT
Applicant returned to address corrections 2/8/2021 RICHARD GARCIA
Plan Check Approved 3/17/2021 RICHARD GARCIA
Issued 4/9/2021 APPLICANT
Permit Finaled 11/3/2022 OSVALDO PARAMO

Permit Application Clearance Information

Specific Plan Cleared 1/19/2021 NASHYA JENSEN
ZI Cleared 1/26/2021 NASHYA JENSEN
ZI Cleared 1/28/2021 SARAHI ORTEGA
Grading Pre-Inspection Cleared 3/17/2021 RICHARD GARCIA

Contact Information

Contractor Xyz Security Construction Corp; Lic. No.: 1064827-B 15344A VALLEY BLVD      CITY OF INDUSTRY, CA 91746
Engineer Kim,, Taewon; Lic. No.: C80632 2800 PLAZA DEL AMO UNIT 161      TORRANCE, CA 90503

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/9/2021 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 6/9/2021 Corrections Issued DAVID FEILER
PLUMBING-Rough 6/9/2021 Corrections Issued DAVID FEILER
Sewer 6/9/2021 Partial Inspection DAVID FEILER
ELECTRICAL-Rough 6/17/2021 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 6/17/2021 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 7/6/2021 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 7/6/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 8/3/2021 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 8/3/2021 Approved OSVALDO PARAMO
HVAC-Rough 8/3/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 8/4/2021 Conditional Approval OSVALDO PARAMO
BUILDING-Rough-Frame 9/9/2021 Approved OSVALDO PARAMO
Shower Pan 9/9/2021 Approved OSVALDO PARAMO
Insulation 10/6/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 10/6/2021 Approved OSVALDO PARAMO
Drywall Nailing 11/10/2021 Approved OSVALDO PARAMO
Final 8/26/2022 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/26/2022 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 8/26/2022 Not Ready for Inspection OSVALDO PARAMO
Final 10/13/2022 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 10/13/2022 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 10/13/2022 Approved OSVALDO PARAMO
Final 10/27/2022 Corrections Issued OSVALDO PARAMO
Final 11/3/2022 Permit Finaled OSVALDO PARAMO