1310 N KENTER AVE 90049

Certificate Information: 1310 N KENTER AVE 90049

Application / Permit
20016-30000-26322
Plan Check / Job No.
B20WL04518
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Structural repair of balconies and decks. Alteration and replacement of windows and doors. Remodeling of (e) wardrobe room and kitchen.
Permit Issued
Issued on 1/11/2021
Issuing Office
Current Status
Permit Finaled on 2/18/2022

Permit Application Status History

Submitted 10/15/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 RICHARD GARCIA
Corrections Issued 10/27/2020 RICHARD GARCIA
Plan Check Approved 12/15/2020 RICHARD GARCIA
Issued 1/11/2021 APPLICANT
Building Plans Picked Up 1/19/2021 APPLICANT
Permit Finaled 2/18/2022 JUAN VALENZUELA

Permit Application Clearance Information

ZI Cleared 11/5/2020 DENZEL HENDERSON

Contact Information

Contractor Jr Builders; Lic. No.: 994546-B 2934 1/2 BEVERLY GLEN CIRCLE      LOS ANGELES, CA 90077
Engineer Khanlou,, Amir; Lic. No.: C87550 10671 HOLMAN AVE   APT 207    LOS ANGELES, CA 90024

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/26/2021 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 1/27/2021 Partial Inspection JOHN KIDWELL
Wood Frame 1/29/2021 Not Ready for Inspection JOHN KIDWELL
Wood Frame 2/3/2021 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 3/31/2021 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 3/31/2021 Partial Approval JUAN VALENZUELA
Structural Steel Frame 4/6/2021 Partial Approval JUAN VALENZUELA
Wood Frame 4/6/2021 Partial Approval JUAN VALENZUELA
Insulation 4/16/2021 Partial Approval JUAN VALENZUELA
Drywall Nailing 5/6/2021 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 5/13/2021 Corrections Issued JUAN VALENZUELA
Deck 6/14/2021 Partial Inspection JUAN VALENZUELA
Interior/Exterior Lathing 6/14/2021 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 6/22/2021 Approved JUAN VALENZUELA
ELECTRICAL-Rough 6/22/2021 Approved JUAN VALENZUELA
Insulation 6/22/2021 Approved JUAN VALENZUELA
Drywall Nailing 6/25/2021 Approved ADAM ESCOTO
ELECTRICAL-Final 2/15/2022 Corrections Issued ANDREW NAVE
PLUMBING-Final 2/15/2022 Approved ANDREW NAVE
Final 2/16/2022 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 2/16/2022 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 2/16/2022 Approved JUAN VALENZUELA
Final 2/18/2022 Permit Finaled JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 2/18/2022 SGSOV Approved JUAN VALENZUELA