7868 S NAYLOR AVE 90045
Certificate Information: 7868 S NAYLOR AVE 90045
- Application / Permit
- 20016-30000-24675
- Plan Check / Job No.
- B20WL04265
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel (E) S.F.D, kitchen and living room Convert (E) Den to new bedroom, Closet into full bath
- Permit Issued
- Issued on 10/31/2020
- Issuing Office
- Current Status
- Permit Finaled on 2/24/2021
Permit Application Status History
| Submitted | 9/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2020 | JASON JANGADA |
| Corrections Issued | 10/8/2020 | JASON JANGADA |
| Plan Check Approved | 10/23/2020 | RICHARD GARCIA |
| Issued | 10/31/2020 | APPLICANT |
| Building Plans Picked Up | 11/4/2020 | APPLICANT |
| Permit Finaled | 2/24/2021 | DAVID HEINE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/13/2020 | BRIAN OLSON |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/3/2020 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 12/3/2020 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Rough | 12/3/2020 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 12/3/2020 | Corrections Issued | JUAN VALENZUELA |
| Special/Order Compliance | 12/3/2020 | Partial Inspection | PIERRE VEGA |
| Footing/Foundation/Slab | 12/15/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 12/22/2020 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 12/22/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Wood Frame | 12/22/2020 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 12/24/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 12/24/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 12/24/2020 | Partial Approval | DAVID HEINE |
| PLUMBING-Rough | 12/24/2020 | Approved | DAVID HEINE |
| Insulation | 12/29/2020 | Approved | DAVID HEINE |
| Drywall Nailing | 1/4/2021 | Not Ready for Inspection | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2021 | Approved | DAVID HEINE |
| Drywall Nailing | 1/7/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 1/7/2021 | Approved | JOHNNY MIRANDA |
| Shower Pan | 1/7/2021 | Approved | JOHNNY MIRANDA |
| Final | 2/22/2021 | Corrections Issued | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 2/22/2021 | SGSOV Gas Company | DAVID HEINE |
| Smoke Detectors | 2/22/2021 | Approved | DAVID HEINE |
| Final | 2/24/2021 | Permit Finaled | DAVID HEINE |