1100 E GRANT AVE 90291

Certificate Information: 1100 E GRANT AVE 90291

Application / Permit
20016-30000-24191
Plan Check / Job No.
B19WL07109
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert garage and recroom to ADU. per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 5/31/2022
Issuing Office
Current Status
CofO Issued on 2/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2019 APPLICANT
Assigned to Plan Check Engineer 1/6/2020 MANUEL GARCIA
Corrections Issued 2/12/2020 MANUEL GARCIA
Quality Review Completed 2/20/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/22/2020 MANUEL GARCIA
Applicant returned to address corrections 9/25/2020 MANUEL GARCIA
Applicant returned to address corrections 11/12/2020 MANUEL GARCIA
Applicant returned to address corrections 5/12/2021 KAVIAN REFAHI
Plan Check Approved 6/11/2021 KAVIAN REFAHI
No Progress 6/11/2021 KAVIAN REFAHI
Plan Check Approved 5/19/2022 KAVIAN REFAHI
Issued 5/31/2022 APPLICANT
Building Plans Picked Up 6/1/2022 APPLICANT
CofO in Progress 2/3/2023 MICHAEL PELHAM
Permit Finaled 2/7/2023 DANIEL ORRANTE
CofO Issued 2/7/2023 DANIEL ORRANTE
Permit Finaled 2/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/9/2021 DINAH GARIN
Miscellaneous Cleared 3/9/2021 KENTON TRINH
Miscellaneous Cleared 3/9/2021 KENTON TRINH
Sewer availability Cleared 3/9/2021 DINAH GARIN
ZA Case Cleared 3/9/2021 KENTON TRINH
Eng Process Fee Ord 176,300 Cleared 3/11/2021 DINAH GARIN
Miscellaneous Cleared 3/23/2021 IRA BROWN
Miscellaneous Cleared 3/23/2021 IRA BROWN
Miscellaneous Cleared 3/23/2021 IRA BROWN
Specific Plan Cleared 3/23/2021 EILEEN HUNT
Specific Plan Cleared 3/23/2021 IRA BROWN
ZI Cleared 3/23/2021 IRA BROWN
Construction near power lines Cleared 6/2/2021 RIDWAN HARDY
Coastal Zone Cleared 5/17/2022 ANNA VIDAL
Miscellaneous Cleared 5/17/2022 ANNA VIDAL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/20/2022 Approved ANDREW NAVE
Rough-Elec/Plmb/HVAC 11/8/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 11/16/2022 Not Ready for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 11/16/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 11/16/2022 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 12/5/2022 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 12/5/2022 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 12/5/2022 Approved EVAN COOPER
PLUMBING-Rough 12/5/2022 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 12/5/2022 Partial Inspection JEREMY TODD
BUILDING-Rough-Frame 12/16/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 12/16/2022 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 12/16/2022 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 12/19/2022 Approved EVAN COOPER
ELECTRICAL-Rough 12/19/2022 Corrections Issued EVAN COOPER
PLUMBING-Rough 12/19/2022 Approved EVAN COOPER
ELECTRICAL-Rough 12/21/2022 Approved JESUS RODRIGUEZ
Insulation 12/21/2022 Corrections Issued JESUS RODRIGUEZ
Drywall Nailing 12/28/2022 Partial Approval JESUS RODRIGUEZ
Insulation 12/28/2022 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 1/6/2023 Approved JESUS RODRIGUEZ
Insulation 1/6/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 1/30/2023 Approved JESUS RODRIGUEZ
Final 1/30/2023 Partial Approval JESUS RODRIGUEZ
HVAC-Final 1/30/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 1/30/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/30/2023 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 1/30/2023 Approved JESUS RODRIGUEZ