22232 W DEL VALLE ST 91364
Certificate Information: 22232 W DEL VALLE ST 91364
- Application / Permit
- 20016-30000-23771
- Plan Check / Job No.
- B20WL04129
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Deck addition 312 sq.ft. New railing and Trellis.
- Permit Issued
- Issued on 4/15/2021
- Issuing Office
- Current Status
- Issued on 4/15/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2020 | PARISA ZAHABI |
| Corrections Issued | 9/29/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 11/24/2020 | ALFREDO JARA |
| Plan Check Approved | 12/22/2020 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 12/28/2020 | APPLICANT |
| Issued | 4/15/2021 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/22/2020 | PARISA ZAHABI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/22/2021 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 4/29/2021 | Approved | HENRY KIM |
| Wood Frame | 7/27/2021 | Approved | PETER FOLLING |
| Final | 10/20/2021 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 10/20/2021 | SGSOV Not Ready | SHAVONNE ESPINOZA |
| Smoke Detectors | 10/20/2021 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Final | 11/15/2021 | Corrections Issued | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 11/15/2021 | SGSOV Gas Company | PETER FOLLING |
| Smoke Detectors | 11/15/2021 | Approved | PETER FOLLING |