3830 N VANALDEN AVE 91356
Certificate Information: 3830 N VANALDEN AVE 91356
- Application / Permit
- 20016-30000-23247
- Plan Check / Job No.
- B20WL04059
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Structural conversion of (e) attached garage into a new bedroom.
- Permit Issued
- Issued on 4/19/2021
- Issuing Office
- Current Status
- CofO Issued on 10/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2020 | JASON JANGADA |
| Corrections Issued | 9/23/2020 | JASON JANGADA |
| Applicant returned to address corrections | 10/14/2020 | RICHARD GARCIA |
| Applicant returned to address corrections | 11/5/2020 | JASON JANGADA |
| Applicant returned to address corrections | 12/20/2020 | RICHARD GARCIA |
| Building Plans Picked Up | 1/4/2021 | APPLICANT |
| Plan Check Approved | 1/15/2021 | RICHARD GARCIA |
| Issued | 4/19/2021 | APPLICANT |
| CofO in Progress | 12/28/2021 | PETER FOLLING |
| CofO Issued | 10/15/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/15/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/28/2020 | TRACY WILLIAMS |
| ZI | Cleared | 10/28/2020 | TRACY WILLIAMS |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 1/4/2021 | GUILLERMO PETRA |
Contact Information
| Contractor | Jencor Construction Inc; Lic. No.: 968170-B | 19528 VENTURA BLVD 273 TARZANA, CA 91356 |
| Engineer | Herrera,, Edgar E; Lic. No.: C67603 | 1929 GREENLEAF DR WEST COVINA, CA 91792 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/23/2021 | Approved | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 9/24/2021 | Partial Approval | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 9/28/2021 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 9/28/2021 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 9/28/2021 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 9/28/2021 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 10/14/2021 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/14/2021 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 10/14/2021 | Approved | DAVID SANDOVAL |
| Wood Frame | 10/14/2021 | Partial Approval | DAVID SANDOVAL |
| ELECTRICAL-Rough | 10/28/2021 | Approved | DAVID SANDOVAL |
| Insulation | 11/2/2021 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2021 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 11/15/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 12/2/2021 | Approved | DAVID SANDOVAL |
| Wood Frame | 12/2/2021 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 12/20/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 12/20/2021 | Approved | DAVID SANDOVAL |
| Final | 12/20/2021 | Corrections Issued | DAVID SANDOVAL |
| HVAC-Final | 12/20/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 12/20/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 12/20/2021 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 12/20/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 12/27/2021 | Approved | PETER FOLLING |
| Final | 12/27/2021 | OK to Issue CofO | PETER FOLLING |
| HVAC-Final | 12/27/2021 | Approved | PETER FOLLING |
| PLUMBING-Final | 12/27/2021 | Approved | PETER FOLLING |