6157 W 77TH ST 90045

Certificate Information: 6157 W 77TH ST 90045

Application / Permit
20016-30000-22877
Plan Check / Job No.
B20WL03988
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) uncovered raised deck at rear of the SFD per engineer's calcs, (N) doors and windows throughout.
Permit Issued
Issued on 2/18/2021
Issuing Office
Current Status
Issued on 2/18/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/16/2020 APPLICANT
Assigned to Plan Check Engineer 9/23/2020 ALFREDO JARA
Corrections Issued 9/24/2020 ALFREDO JARA
Applicant returned to address corrections 12/16/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 1/20/2021 JAHANSHAH POURHASSAN
Plan Check Approved 2/4/2021 ALFREDO JARA
Building Plans Picked Up 2/8/2021 APPLICANT
Issued 2/18/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/18/2020 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 11/18/2020 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 11/20/2020 PATRICK MISCHLICH

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/2/2021 Not Ready for Inspection DAVID HEINE
Interior/Exterior Lathing 3/2/2021 Not Ready for Inspection DAVID HEINE
Pre-Inspection 3/2/2021 Partial Inspection DAVID HEINE
BUILDING-Rough-Frame 3/8/2021 Not Ready for Inspection KENNETH NAGLE
Interior/Exterior Lathing 3/8/2021 Partial Approval KENNETH NAGLE
BUILDING-Rough-Frame 3/16/2021 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 3/16/2021 Partial Approval JUAN VALENZUELA
Special/Order Compliance 5/18/2021 No Access for Inspection BRENDAN LOONEY
Final 9/13/2021 Not Ready for Inspection WILLIAM MICHALAK
Interior/Exterior Lathing 9/13/2021 Not Ready for Inspection WILLIAM MICHALAK
Pre-Inspection 9/13/2021 Partial Approval WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 9/13/2021 SGSOV Approved WILLIAM MICHALAK
Smoke Detectors 9/13/2021 Approved WILLIAM MICHALAK
Deputy Drilled-In Anchors 11/18/2024 Conditional Approval TEMISTOCLES CAAL