1344 W 8TH ST 90732

Certificate Information: 1344 W 8TH ST 90732

Application / Permit
20016-30000-22741
Plan Check / Job No.
B20WL03969
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel (e) Single family dwelling. No square footage added. Per engineering design.
Permit Issued
Issued on 4/29/2022
Issuing Office
Metro
Current Status
Permit Finaled on 8/25/2023

Permit Application Status History

Submitted 9/11/2020 APPLICANT
Assigned to Plan Check Engineer 9/15/2020 ALFREDO JARA
Corrections Issued 9/16/2020 ALFREDO JARA
Applicant returned to address corrections 10/27/2020 ALFREDO JARA
Building Plans Picked Up 11/6/2020 APPLICANT
Applicant returned to address corrections 4/13/2021 FELIPE HERNANDEZ
Plan Check Approved 4/29/2022 JOSEPH RAFOLS
Issued 4/29/2022 APPLICANT
Permit Finaled 8/25/2023 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/28/2020 CHINH DINH
Roof/Waste drainage to street Cleared 9/28/2020 CHINH DINH
Grading Pre-Inspection Cleared 10/1/2020 BARTON HOLMES

Contact Information

Contractor Owner-Builder       ,
Engineer Moseman,, Steven Nye; Lic. No.: C39790 7991 SILVERBRIDGE ROAD      PALO CEDRO, CA 96073

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/6/2023 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 1/6/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 1/6/2023 Corrections Issued JAMES CHAVEZ
BUILDING-Rough-Frame 1/10/2023 Approved ANSON MAGLASANG
Rough-Elec/Plmb/HVAC 1/10/2023 Approved ANSON MAGLASANG
Insulation 1/11/2023 Approved JOHN KLARIN
Drywall Nailing 1/13/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 4/21/2023 Approved ANSON MAGLASANG
ELECTRICAL-Rough 4/21/2023 Approved ANSON MAGLASANG
PLUMBING-Rough 4/21/2023 Approved ANSON MAGLASANG
Insulation 4/24/2023 Approved ANSON MAGLASANG
Drywall Nailing 4/27/2023 Approved ANSON MAGLASANG
Interior/Exterior Lathing 5/5/2023 Approved EUGENE CASSIDY
Shower Pan 5/5/2023 Approved EUGENE CASSIDY
Final 8/23/2023 Corrections Issued ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 8/23/2023 SGSOV Approved ANSON MAGLASANG
Smoke Detectors 8/23/2023 Corrections Issued ANSON MAGLASANG
Final 8/25/2023 Permit Finaled ANSON MAGLASANG
Smoke Detectors 8/25/2023 Approved ANSON MAGLASANG