- Convert existing detached garage at rear of the lot to an accessory dwelling unit per GCS 65852.2(e)(1)(A) and trellis addition.
- Permit Issued
- Issued on 3/4/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2020 | JAHANSHAH POURHASSAN |
| Corrections Issued | 9/25/2020 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 12/1/2020 | JASON JANGADA |
| Applicant returned to address corrections | 1/21/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 3/5/2021 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 4/8/2021 | MARJAN SHENASI |
| Issued | 3/4/2022 | APPLICANT |
| Building Plans Picked Up | 3/7/2022 | APPLICANT |
| CofO in Progress | 1/31/2024 | JESUS PINEDA |
| Permit Finaled | 2/1/2024 | DANIEL ORRANTE |
| CofO Issued | 2/1/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/1/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/14/2020 | TRACY TATE |
| Address approval | Cleared | 10/16/2020 | TRACY TATE |
| Roof/Waste drainage to street | Cleared | 10/16/2020 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2020 | TRACY TATE |
| ZA Case | Cleared | 12/7/2020 | LOUIS ORTEGA |
| Construction near power lines | Cleared | 12/8/2020 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 12/10/2020 | MATTHEW CRAIG |
| Specific Plan | Cleared | 1/6/2021 | PEDRO AYALA |
| Grading Pre-Inspection | Cleared | 3/14/2021 | JAHANSHAH POURHASSAN |
Contact Information
| Architect | Rees,, Robert S; Lic. No.: C26934 | 3483 BARRY AVENUE LOS ANGELES, CA 90066 |
| Contractor | Owner-Builder | , |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 205 S CHAPEL AVE #D-1 ALHAMBRA, CA 91801 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/15/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 7/29/2022 | Conditional Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 8/4/2022 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 8/4/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 8/10/2022 | Partial Approval | JOHNNY MIRANDA |
| Sewer | 8/10/2022 | Approved | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 8/11/2022 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 8/12/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 10/27/2022 | Conditional Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 11/21/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 1/6/2023 | Corrections Issued | JOHNNY MIRANDA |
| Pre-Inspection | 7/12/2023 | Partial Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2023 | Corrections Issued | JESUS PINEDA |
| Green Building Rough | 8/17/2023 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Rough | 8/17/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 9/12/2023 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 9/12/2023 | Approved | JESUS PINEDA |
| Insulation | 9/12/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 9/12/2023 | Partial Approval | JESUS PINEDA |
| Drywall Nailing | 9/19/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 9/28/2023 | Approved | BEN MOLSTAD |
| Shower Pan | 9/28/2023 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 12/12/2023 | Corrections Issued | JESUS PINEDA |
| Final | 12/12/2023 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 12/12/2023 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Final | 12/12/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 12/12/2023 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Not Required | JESUS PINEDA |
| Smoke Detectors | 12/12/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 1/30/2024 | Approved | JESUS PINEDA |
| Final | 1/30/2024 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 1/30/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 1/30/2024 | Approved | JESUS PINEDA |