3158 S COLBY AVE 90066

Certificate Information: 3158 S COLBY AVE 90066

Application / Permit
20016-30000-22580
Plan Check / Job No.
B20WL03939
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage at rear of the lot to an accessory dwelling unit per GCS 65852.2(e)(1)(A) and trellis addition.
Permit Issued
Issued on 3/4/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2020 APPLICANT
Assigned to Plan Check Engineer 9/15/2020 JAHANSHAH POURHASSAN
Corrections Issued 9/25/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 12/1/2020 JASON JANGADA
Applicant returned to address corrections 1/21/2021 MANUEL GARCIA
Applicant returned to address corrections 3/5/2021 JAHANSHAH POURHASSAN
Plan Check Approved 4/8/2021 MARJAN SHENASI
Issued 3/4/2022 APPLICANT
Building Plans Picked Up 3/7/2022 APPLICANT
CofO in Progress 1/31/2024 JESUS PINEDA
Permit Finaled 2/1/2024 DANIEL ORRANTE
CofO Issued 2/1/2024 DANIEL ORRANTE
Permit Finaled 2/1/2024 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 10/14/2020 TRACY TATE
Address approval Cleared 10/16/2020 TRACY TATE
Roof/Waste drainage to street Cleared 10/16/2020 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 10/19/2020 TRACY TATE
ZA Case Cleared 12/7/2020 LOUIS ORTEGA
Construction near power lines Cleared 12/8/2020 RIDWAN HARDY
Hydrant and Access approval Cleared 12/10/2020 MATTHEW CRAIG
Specific Plan Cleared 1/6/2021 PEDRO AYALA
Grading Pre-Inspection Cleared 3/14/2021 JAHANSHAH POURHASSAN

Contact Information

Architect Rees,, Robert S; Lic. No.: C26934 3483 BARRY AVENUE      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,
Engineer Zhuang,, Wenbin; Lic. No.: S5236 205 S CHAPEL AVE #D-1      ALHAMBRA, CA 91801

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/15/2022 Partial Approval JOHNNY MIRANDA
Deputy Drilled-In Anchors 7/29/2022 Conditional Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 8/4/2022 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 8/4/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 8/10/2022 Partial Approval JOHNNY MIRANDA
Sewer 8/10/2022 Approved JOHNNY MIRANDA
Deputy Drilled-In Anchors 8/11/2022 Conditional Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 8/12/2022 Partial Approval JOHNNY MIRANDA
Green Building Rough 8/12/2022 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 10/27/2022 Conditional Approval JOHNNY MIRANDA
PLUMBING-Rough 11/21/2022 Approved JOHNNY MIRANDA
HVAC-Rough 1/6/2023 Corrections Issued JOHNNY MIRANDA
Pre-Inspection 7/12/2023 Partial Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 8/17/2023 Corrections Issued JESUS PINEDA
Green Building Rough 8/17/2023 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 8/17/2023 Approved JESUS PINEDA
BUILDING-Rough-Frame 9/12/2023 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Approved JESUS PINEDA
Green Building Rough 9/12/2023 Approved JESUS PINEDA
Insulation 9/12/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 9/12/2023 Partial Approval JESUS PINEDA
Drywall Nailing 9/19/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 9/28/2023 Approved BEN MOLSTAD
Shower Pan 9/28/2023 Approved BEN MOLSTAD
ELECTRICAL-Final 12/12/2023 Corrections Issued JESUS PINEDA
Final 12/12/2023 Corrections Issued JESUS PINEDA
Green Building Final 12/12/2023 Not Ready for Inspection JESUS PINEDA
HVAC-Final 12/12/2023 Corrections Issued JESUS PINEDA
PLUMBING-Final 12/12/2023 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 12/12/2023 SGSOV Not Required JESUS PINEDA
Smoke Detectors 12/12/2023 Approved JESUS PINEDA
ELECTRICAL-Final 1/30/2024 Approved JESUS PINEDA
Final 1/30/2024 OK to Issue CofO JESUS PINEDA
Green Building Final 1/30/2024 Approved JESUS PINEDA
HVAC-Final 1/30/2024 Approved JESUS PINEDA