10425 W SUNSET BLVD POOL-HOUSE 90077
Certificate Information: 10425 W SUNSET BLVD POOL-HOUSE 90077
- Application / Permit
- 20016-30000-20767
- Plan Check / Job No.
- X20WL04566
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel of POOL HOUSE ( no structural changes) ( 6 ) WINDOW and ( 6 ) DOOR change-out (same size & type) for residential buildings. Dual glazing, labeled and certified by National Fenestration Rating Council (NFRC), is required for doors and windows replaced in all residential buildings, three stories or less, per Section 152(b) of Title 24. ( 1 )BATHROOM remodel for residential buildings (combined with elect/plumb/hvac) Re-stucco for single family dwellings and duplexes only. Replace drywall (no new walls added) for single family dwellings and duplexes only. Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over EXISTING solid sheathing __13_Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone (VHFHSZ). For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council (CRRC). Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 149(b). Water damage, termite damage/ dry rot repair less than 10% of replacement cost of residential buildings.
- Permit Issued
- Issued on 8/25/2020
- Issuing Office
- Current Status
- Permit Finaled on 5/9/2025
Permit Application Status History
| Issued | 8/25/2020 | APPLICANT |
| Permit Finaled | 5/8/2025 | CHRISTOPHER WILSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Builder'S Team Inc; Lic. No.: 636904-B | 2259 HONOLULU AVENUE MONTROSE, CA 91020 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/7/2021 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 6/7/2022 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2022 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 6/17/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 9/15/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 12/7/2022 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/9/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/19/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 1/19/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 1/19/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/19/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Rough-Elec/Plmb/HVAC | 1/19/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/23/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 1/23/2023 | Approved | CARLOS MATAMOROS |
| Gas Test | 1/23/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 1/23/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/23/2023 | Approved | CARLOS MATAMOROS |
| Final | 5/8/2025 | Permit Finaled | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 5/8/2025 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 5/8/2025 | Approved | CHRISTOPHER WILSON |