1525 S CLOVERDALE AVE 90019
Certificate Information: 1525 S CLOVERDALE AVE 90019
- Application / Permit
- 20016-30000-20376
- Plan Check / Job No.
- B20WL03548
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of portion of an (E) detached garage to ADU per CA GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 11/25/2020
- Issuing Office
- Current Status
- CofO Issued on 6/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2020 | JAHANSHAH POURHASSAN |
| Corrections Issued | 8/26/2020 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 11/16/2020 | RICHARD GARCIA |
| Plan Check Approved | 11/17/2020 | RICHARD GARCIA |
| Building Plans Picked Up | 11/18/2020 | APPLICANT |
| Issued | 11/25/2020 | APPLICANT |
| CofO in Progress | 5/27/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 6/27/2021 | DEROLD HAUFF |
| CofO Issued | 6/27/2021 | DEROLD HAUFF |
| Permit Finaled | 6/27/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 9/30/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 10/2/2020 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Durand,, Paul Henri; Lic. No.: S4222 | 611 N G ST OXNARD, CA 93030 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/5/2021 | Partial Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 1/7/2021 | Partial Inspection | DAVID CHAN |
| Deputy Drilled-In Anchors | 1/14/2021 | Approved | DAVID CHAN |
| Footing/Foundation/Slab | 1/14/2021 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 1/28/2021 | Partial Approval | STUART CHAPMAN |
| Gas Test | 1/28/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Gas Test | 2/1/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 2/8/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Sewer | 2/8/2021 | Approved | KATHRYN BUTTERWORTH |
| Underground Mechanical | 2/8/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 2/11/2021 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/11/2021 | Approved | STUART CHAPMAN |
| Final | 2/11/2021 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2021 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 2/11/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 2/18/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 2/18/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 2/18/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 2/22/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| HVAC-Rough | 2/22/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 2/22/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 2/22/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 3/1/2021 | Approved | STUART CHAPMAN |
| Underground Mechanical | 3/1/2021 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 3/5/2021 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 3/5/2021 | Partial Approval | ROBERT VORHIS |
| Shower Pan | 3/5/2021 | Approved | ROBERT VORHIS |
| Final | 5/11/2021 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 5/11/2021 | SGSOV Not Required | STUART CHAPMAN |
| Smoke Detectors | 5/11/2021 | Approved | STUART CHAPMAN |
| Final | 5/19/2021 | Corrections Issued | STUART CHAPMAN |
| Final | 5/25/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |