3983 S BERRYMAN AVE 90066

Certificate Information: 3983 S BERRYMAN AVE 90066

Application / Permit
20016-30000-19709
Plan Check / Job No.
B20WL03469
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing garage to storage and ADU per ordinance.
Permit Issued
Issued on 2/3/2021
Issuing Office
Current Status
CofO Issued on 8/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 MANUEL GARCIA
Corrections Issued 8/24/2020 MANUEL GARCIA
Plan Check Approved 11/5/2020 MANUEL GARCIA
Issued 2/3/2021 APPLICANT
Building Plans Picked Up 2/8/2021 APPLICANT
CofO in Progress 8/6/2021 ENRIQUE MIRELES
Permit Finaled 8/11/2021 VINCENT COTTON
CofO Issued 8/11/2021 VINCENT COTTON
Permit Finaled 8/11/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 9/16/2020 ANTHONY MAINEZ
Sewer availability Cleared 9/16/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 9/17/2020 ANTHONY MAINEZ
Specific Plan Cleared 10/13/2020 VALERIA CEJA

Contact Information

Contractor Mancini Contracting; Lic. No.: 958370-B 4040 GRANDVIEW BOULEVARD #67      LOS ANGELES, CA 90066
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/11/2021 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 2/11/2021 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 2/25/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 2/25/2021 Partial Approval ENRIQUE MIRELES
Footing/Foundation/Slab 3/17/2021 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 3/18/2021 Corrections Issued ENRIQUE MIRELES
Deputy Drilled-In Anchors 3/19/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 3/22/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 4/14/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 4/22/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 4/22/2021 Approved ENRIQUE MIRELES
Service/Power Release 4/22/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 5/18/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 6/1/2021 Approved ENRIQUE MIRELES
Drywall Nailing 6/3/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 6/4/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 6/7/2021 Approved AMY COLIN
Interior/Exterior Lathing 6/9/2021 Approved ENRIQUE MIRELES
Final 7/14/2021 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/14/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 7/14/2021 Approved ENRIQUE MIRELES
Final 7/16/2021 Corrections Issued ENRIQUE MIRELES
Final 8/6/2021 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 8/10/2021 Approved ENRIQUE MIRELES