13249 W IDA AVE 90066

Certificate Information: 13249 W IDA AVE 90066

Application / Permit
20016-30000-19397
Plan Check / Job No.
B20WL03414
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Garage conversion to ADU per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 10/16/2020
Issuing Office
Current Status
CofO Issued on 7/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2020 APPLICANT
Assigned to Plan Check Engineer 8/17/2020 MARJAN SHENASI
Corrections Issued 8/18/2020 MARJAN SHENASI
Plan Check Approved 10/8/2020 RICHARD GARCIA
Building Plans Picked Up 10/8/2020 APPLICANT
Issued 10/16/2020 APPLICANT
CofO in Progress 7/19/2021 PIERRE VEGA
CofO Issued 7/19/2021 VINCENT COTTON
Permit Finaled 7/19/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 9/1/2020 SAUL GARCIA
Sewer availability Cleared 9/1/2020 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 9/2/2020 SAUL GARCIA
Hydrant and Access approval Cleared 9/16/2020 MATTHEW CRAIG
Specific Plan Cleared 9/23/2020 FREDDY GARCIA

Contact Information

Contractor Bayview Construction Inc; Lic. No.: 667400-B 2701 11TH STREET      SANTA MONICA, CA 90405
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/17/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/24/2020 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 12/9/2020 Partial Approval ENRIQUE MIRELES
Underground Mechanical 12/31/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 1/5/2021 Corrections Issued PIERRE VEGA
BUILDING-Rough-Frame 1/15/2021 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 1/15/2021 Partial Approval JOHNNY MIRANDA
HVAC-Rough 1/27/2021 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 1/27/2021 Approved ENRIQUE MIRELES
Insulation 1/28/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 1/28/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/29/2021 Approved ENRIQUE MIRELES
Drywall Nailing 2/4/2021 Approved EVAN COOPER
Interior/Exterior Lathing 2/4/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 3/15/2021 Approved JOHNNY MIRANDA
Final 3/15/2021 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 3/15/2021 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 3/15/2021 Approved JOHNNY MIRANDA
Final 4/7/2021 Corrections Issued ENRIQUE MIRELES
Final 5/10/2021 Not Ready for Inspection JOHNNY MIRANDA
Final 6/11/2021 Corrections Issued ENRIQUE MIRELES
Final 7/1/2021 Conditional Approval ENRIQUE MIRELES