11561 W SYLVAN ST 1-8 91606

Certificate Information: 11561 W SYLVAN ST 1-8 91606

Application / Permit
20016-30000-19287
Plan Check / Job No.
B20WL03392
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert rear detached garage & laundry room to two ADUs & laundry room per GCS 65852-2. See comments.
Permit Issued
Issued on 5/31/2021
Issuing Office
Current Status
CofO Issued on 5/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2020 APPLICANT
Assigned to Plan Check Engineer 12/2/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 1/11/2021 VLADIMIR ARUTYUNYAN
Quality Review Completed 1/21/2021 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 1/28/2021 APPLICANT
Applicant returned to address corrections 4/27/2021 SERGIO SILVA
Plan Check Approved 5/11/2021 SERGIO SILVA
Issued 5/31/2021 APPLICANT
TCO Issued (Expire Date: 08-31-2022) 3/4/2022 JEFFREY DURAN
CofO in Progress 5/5/2022 ROBERT DAVIS
CofO Issued 5/20/2022 JEFFREY DURAN
Permit Finaled 5/20/2022 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 1/29/2021 GABRIEL ROBLES
Sewer availability Cleared 1/29/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 2/1/2021 GABRIEL ROBLES
"Q" conditions Cleared 2/3/2021 RICHARD REASER
Hydrant and Access approval Cleared 3/22/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/27/2021 Corrections Issued ROBERT DAVIS
Footing/Foundation/Slab 8/6/2021 Approved DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 8/11/2021 Partial Approval ROBERT DAVIS
Deputy Drilled-In Anchors 8/20/2021 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 8/20/2021 Approved ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 10/12/2021 Not Ready for Inspection JOE VELASQUEZ
Deputy Wood Construction 10/15/2021 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 10/15/2021 Partial Approval ROBERT DAVIS
Wood Frame 11/5/2021 Approved ROBERT DAVIS
Interior/Exterior Lathing 12/3/2021 Partial Approval ROBERT DAVIS
Insulation 12/17/2021 Approved DANIEL VARNUM
Drywall Nailing 12/30/2021 Approved ROBERT DAVIS
Special/Order Compliance 2/2/2022 Approved ROBERT DAVIS
Final 3/1/2022 Corrections Issued ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 3/1/2022 SGSOV Not Ready ROBERT DAVIS
Smoke Detectors 3/1/2022 Approved ROBERT DAVIS
Final 3/4/2022 OK for TCO ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 3/4/2022 SGSOV Approved ROBERT DAVIS
Special/Order Compliance 3/4/2022 Approved ROBERT DAVIS