1233 S WESTGATE AVE 90025
Certificate Information: 1233 S WESTGATE AVE 90025
- Application / Permit
- 20016-30000-19014
- Plan Check / Job No.
- B20WL03340
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (2) TWO RECREATION ROOMS IN APARTMENT BUILDING INTO (2) TWO ACCESSORY DWELLING UNITS, PER GCS 65852.2(e)(1)(C).
- Permit Issued
- Issued on 12/17/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2020 | SERGIO SILVA |
| Corrections Issued | 9/2/2020 | SERGIO SILVA |
| Quality Review Completed | 9/10/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 12/10/2020 | SERGIO SILVA |
| Issued | 12/17/2020 | APPLICANT |
| Building Plans Picked Up | 12/18/2020 | APPLICANT |
| CofO in Progress | 7/12/2022 | JEFF BYTHEWAY |
| Permit Finaled | 7/12/2022 | HENRY BAGHDASSARIAN |
| Permit Finaled | 7/12/2022 | HENRY BAGHDASSARIAN |
| CofO Issued | 7/12/2022 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Address approval | Cleared | 9/24/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2020 | DINAH GARIN |
| Sewer availability | Cleared | 9/24/2020 | DINAH GARIN |
| Miscellaneous | Cleared | 9/25/2020 | DENZEL HENDERSON |
| Specific Plan | Cleared | 9/30/2020 | PEDRO AYALA |
| "Q" conditions | Cleared | 11/10/2020 | LOUIS ORTEGA |
| ZI | Cleared | 11/10/2020 | LOUIS ORTEGA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cohanzad,, Isaac Wise; Lic. No.: C39474 | 11601 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/3/2021 | Approved | TED RIES |
| Final | 10/29/2021 | Partial Inspection | JOHN DODGE |
| Reinforced Concrete Frame | 10/29/2021 | Approved | JOHN DODGE |
| Reinforced Masonry Frame | 10/29/2021 | Approved | JOHN DODGE |
| SGSOV-Seismic Gas S/O Valve | 10/29/2021 | SGSOV Approved | JOHN DODGE |
| Smoke Detectors | 10/29/2021 | Partial Approval | JOHN DODGE |
| Wood Frame | 11/12/2021 | Not Ready for Inspection | JOHN DODGE |
| Pre-Inspection | 11/29/2021 | Partial Approval | GRANT WOODS |
| Wood Frame | 12/1/2021 | Approved | JOHN DODGE |
| Drywall Nailing | 12/3/2021 | Partial Approval | JEFF BYTHEWAY |
| Drywall Nailing | 12/7/2021 | Approved | JOHN DODGE |
| Interior/Exterior Lathing | 12/8/2021 | Approved | JOHN DODGE |
| Final | 2/17/2022 | Conditional Approval | JOHN DODGE |
| Smoke Detectors | 2/17/2022 | Approved | JOHN DODGE |