835-837 W VENEZIA AVE 90291
Certificate Information: 835-837 W VENEZIA AVE 90291
- Application / Permit
- 20016-30000-18399
- Plan Check / Job No.
- B20WL03258
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT PART OF THE (E) GARAGE SPACE ON THE 1ST FLOOR TO FULL BATHROOM AND HALLWAY TO BE COMBINED WITH TH 2ND FLOOR OF (E) DUPLEX UNIT.
- Permit Issued
- Issued on 11/29/2021
- Issuing Office
- Current Status
- CofO Issued on 12/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2020 | PARISA ZAHABI |
| Corrections Issued | 8/5/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 4/7/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 6/9/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 7/26/2021 | PARISA ZAHABI |
| Plan Check Approved | 8/19/2021 | PARISA ZAHABI |
| Issued | 11/29/2021 | APPLICANT |
| Building Plans Picked Up | 12/1/2021 | APPLICANT |
| CofO in Progress | 12/15/2023 | HERBERT GIRON |
| Permit Finaled | 12/18/2023 | DANIEL ORRANTE |
| CofO Issued | 12/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 8/14/2020 | MAXFIELD VERMY |
| Specific Plan | Cleared | 8/28/2020 | BINDU KANNAN |
| ZI | Cleared | 8/28/2020 | BINDU KANNAN |
| Miscellaneous | Cleared | 1/28/2021 | NOAH MCCOY |
| Specific Plan | Cleared | 2/22/2021 | FREDDY GARCIA |
| Tenant Habitability Plan | Cleared | 3/11/2021 | RICARDO BOHORQUEZ |
| Green Code | Cleared | 6/9/2021 | PARISA ZAHABI |
| Coastal Zone | Cleared | 8/10/2021 | NOAH MCCOY |
Contact Information
| Architect | Fonda-Bonardi,, Mario; Lic. No.: C11271 | 1450 23RD STREET SANTA MONICA, CA 904042902 |
| Contractor | Snow Construction; Lic. No.: 1016716-B | 6647 ORION AVE VAN NUYS, CA 91406 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/6/2021 | No Access for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 12/13/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 12/13/2021 | Partial Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 12/15/2021 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 12/15/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 5/3/2022 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 5/3/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 5/3/2022 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 5/3/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 5/11/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 5/11/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 5/11/2022 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 5/11/2022 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 5/19/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/19/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 5/19/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Insulation | 5/19/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/19/2022 | Approved | JESUS RODRIGUEZ |
| Deputy Wood Construction | 5/20/2022 | Conditional Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 5/24/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/24/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 5/24/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/24/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/24/2022 | Approved | JESUS RODRIGUEZ |
| Wood Frame | 5/24/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/15/2022 | Partial Approval | DAVID FEILER |
| Pre-Inspection | 9/23/2022 | Corrections Issued | DAVID FEILER |
| Shower Pan | 11/8/2022 | Approved | ANDREW NAVE |
| Wood Frame | 11/8/2022 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 8/11/2023 | Approved | EVAN COOPER |
| Final | 8/11/2023 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 8/11/2023 | Not Ready for Inspection | EVAN COOPER |
| Insulation | 8/11/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/11/2023 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 8/11/2023 | Not Ready for Inspection | EVAN COOPER |
| Drywall Nailing | 8/31/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 8/31/2023 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 12/5/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 12/5/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 12/5/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 12/5/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 12/5/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 12/14/2023 | Approved | HERBERT GIRON |
| Final | 12/14/2023 | OK to Issue CofO | HERBERT GIRON |
| PLUMBING-Final | 12/14/2023 | Approved | HERBERT GIRON |