835-837 W VENEZIA AVE 90291

Certificate Information: 835-837 W VENEZIA AVE 90291

Application / Permit
20016-30000-18399
Plan Check / Job No.
B20WL03258
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT PART OF THE (E) GARAGE SPACE ON THE 1ST FLOOR TO FULL BATHROOM AND HALLWAY TO BE COMBINED WITH TH 2ND FLOOR OF (E) DUPLEX UNIT.
Permit Issued
Issued on 11/29/2021
Issuing Office
Current Status
CofO Issued on 12/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2020 APPLICANT
Assigned to Plan Check Engineer 8/4/2020 PARISA ZAHABI
Corrections Issued 8/5/2020 PARISA ZAHABI
Applicant returned to address corrections 4/7/2021 PARISA ZAHABI
Applicant returned to address corrections 6/9/2021 PARISA ZAHABI
Applicant returned to address corrections 7/26/2021 PARISA ZAHABI
Plan Check Approved 8/19/2021 PARISA ZAHABI
Issued 11/29/2021 APPLICANT
Building Plans Picked Up 12/1/2021 APPLICANT
CofO in Progress 12/15/2023 HERBERT GIRON
Permit Finaled 12/18/2023 DANIEL ORRANTE
CofO Issued 12/18/2023 DANIEL ORRANTE
Permit Finaled 12/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 8/14/2020 MAXFIELD VERMY
Specific Plan Cleared 8/28/2020 BINDU KANNAN
ZI Cleared 8/28/2020 BINDU KANNAN
Miscellaneous Cleared 1/28/2021 NOAH MCCOY
Specific Plan Cleared 2/22/2021 FREDDY GARCIA
Tenant Habitability Plan Cleared 3/11/2021 RICARDO BOHORQUEZ
Green Code Cleared 6/9/2021 PARISA ZAHABI
Coastal Zone Cleared 8/10/2021 NOAH MCCOY

Contact Information

Architect Fonda-Bonardi,, Mario; Lic. No.: C11271 1450 23RD STREET      SANTA MONICA, CA 904042902
Contractor Snow Construction; Lic. No.: 1016716-B 6647 ORION AVE      VAN NUYS, CA 91406

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/6/2021 No Access for Inspection DAVID FEILER
Footing/Foundation/Slab 12/13/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 12/13/2021 Partial Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 12/15/2021 Approved DAVID FEILER
Footing/Foundation/Slab 12/15/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 5/3/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 5/3/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 5/3/2022 Not Ready for Inspection DAVID FEILER
Wood Frame 5/3/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 5/11/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 5/11/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 5/11/2022 Not Ready for Inspection DAVID FEILER
Wood Frame 5/11/2022 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 5/19/2022 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 5/19/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 5/19/2022 Corrections Issued JESUS RODRIGUEZ
Insulation 5/19/2022 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 5/19/2022 Approved JESUS RODRIGUEZ
Deputy Wood Construction 5/20/2022 Conditional Approval RICHARD STEINBACH
BUILDING-Rough-Frame 5/24/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 5/24/2022 Approved JESUS RODRIGUEZ
Insulation 5/24/2022 Conditional Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 5/24/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/24/2022 Approved JESUS RODRIGUEZ
Wood Frame 5/24/2022 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 7/15/2022 Partial Approval DAVID FEILER
Pre-Inspection 9/23/2022 Corrections Issued DAVID FEILER
Shower Pan 11/8/2022 Approved ANDREW NAVE
Wood Frame 11/8/2022 Approved ANDREW NAVE
BUILDING-Rough-Frame 8/11/2023 Approved EVAN COOPER
Final 8/11/2023 Not Ready for Inspection EVAN COOPER
HVAC-Final 8/11/2023 Not Ready for Inspection EVAN COOPER
Insulation 8/11/2023 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 8/11/2023 SGSOV Not Ready EVAN COOPER
Smoke Detectors 8/11/2023 Not Ready for Inspection EVAN COOPER
Drywall Nailing 8/31/2023 Approved HERBERT GIRON
HVAC-Final 8/31/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 12/5/2023 Corrections Issued HERBERT GIRON
HVAC-Final 12/5/2023 Approved HERBERT GIRON
PLUMBING-Final 12/5/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 12/5/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 12/5/2023 Approved HERBERT GIRON
ELECTRICAL-Final 12/14/2023 Approved HERBERT GIRON
Final 12/14/2023 OK to Issue CofO HERBERT GIRON
PLUMBING-Final 12/14/2023 Approved HERBERT GIRON