146 N HARVARD BLVD 90004

Certificate Information: 146 N HARVARD BLVD 90004

Application / Permit
20016-30000-18177
Plan Check / Job No.
B20WL03229
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL TO (E) 2-STORY S.F.D.
Permit Issued
Issued on 9/22/2020
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 5/31/2021

Permit Application Status History

Submitted 7/29/2020 APPLICANT
Assigned to Plan Check Engineer 8/3/2020 MARJAN SHENASI
Corrections Issued 8/4/2020 MARJAN SHENASI
Plan Check Approved 9/15/2020 MANUEL GARCIA
Issued 9/22/2020 APPLICANT
Building Plans Picked Up 9/23/2020 APPLICANT
Permit Finaled 5/28/2021 CHRIS CHRISTENSEN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor South Coast Construction And Development; Lic. No.: 1000004-B 8812 W PICO BLVD #211      LOS ANGELES, CA 90035

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/30/2020 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 9/30/2020 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/9/2020 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 10/9/2020 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 10/9/2020 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 11/18/2020 Approved CHRIS CHRISTENSEN
HVAC-Rough 11/18/2020 Approved CHRIS CHRISTENSEN
Insulation 11/18/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/18/2020 Approved CHRIS CHRISTENSEN
Shower Pan 11/18/2020 Approved CHRIS CHRISTENSEN
Drywall Nailing 12/17/2020 Approved DAVID FEILER
Final 1/12/2021 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 1/12/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 5/19/2021 Corrections Issued CHRIS CHRISTENSEN
Final 5/19/2021 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Final 5/19/2021 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Final 5/19/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/19/2021 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 5/19/2021 Approved CHRIS CHRISTENSEN
Smoke Detectors 5/19/2021 Approved CHRIS CHRISTENSEN
Final 5/28/2021 Permit Finaled CHRIS CHRISTENSEN