213 N AVENUE 56 90042

Certificate Information: 213 N AVENUE 56 90042

Application / Permit
20016-30000-17803
Plan Check / Job No.
B20WL03163
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert (E) detached laundry & storage room to dwelling.
Permit Issued
Issued on 1/6/2021
Issuing Office
Current Status
CofO Issued on 7/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2020 APPLICANT
Assigned to Plan Check Engineer 8/13/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 8/21/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 9/2/2020 KAVIAN REFAHI
Plan Check Approved 12/24/2020 VLADIMIR ARUTYUNYAN
Issued 1/6/2021 APPLICANT
Building Plans Picked Up 1/7/2021 APPLICANT
CofO in Progress 7/17/2024 ALIZAH MAYAGOITIA
CofO Issued 7/22/2024 DEROLD HAUFF
Permit Finaled 7/22/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/14/2020 JEANIE LAM
Sewer availability Cleared 9/14/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/23/2020 JEANIE LAM
HPOZ Cleared 11/12/2020 KATIE DEBIASE

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Sewer 5/18/2021 Approved COREY HUPP
Pre-Inspection 3/21/2023 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 5/2/2023 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 5/25/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 5/25/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/25/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 6/1/2023 Corrections Issued OSVALDO PARAMO
HVAC-Rough 6/1/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 2/12/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 2/21/2024 Partial Approval ALIZAH MAYAGOITIA
Insulation 2/23/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 2/27/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/2/2024 Approved ALIZAH MAYAGOITIA
Final 7/12/2024 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 7/12/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 7/12/2024 Approved ALIZAH MAYAGOITIA
Final 7/16/2024 Conditional Approval ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 7/16/2024 SGSOV Approved ALIZAH MAYAGOITIA
Final 7/17/2024 OK to Issue CofO ALIZAH MAYAGOITIA