3054 N SILVER LAKE BLVD 90039
Certificate Information: 3054 N SILVER LAKE BLVD 90039
- Application / Permit
- 20016-30000-17624
- Plan Check / Job No.
- B20WL03116
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior Remodel- Kitchen, adjacent area, extend side porch, and replace window with door
- Permit Issued
- Issued on 9/21/2020
- Issuing Office
- Current Status
- Permit Finaled on 6/4/2021
Permit Application Status History
| Submitted | 7/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2020 | JASON JANGADA |
| Corrections Issued | 7/31/2020 | JASON JANGADA |
| Applicant returned to address corrections | 9/11/2020 | MANUEL GARCIA |
| Plan Check Approved | 9/11/2020 | MANUEL GARCIA |
| Issued | 9/21/2020 | APPLICANT |
| Building Plans Picked Up | 9/28/2020 | APPLICANT |
| Permit Finaled | 6/3/2021 | HAMIK HARTOUNIAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12540 DESTINO ST CERRITOS, CA 90703 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/12/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/8/2020 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/8/2020 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/8/2020 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 12/8/2020 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/21/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 12/21/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 1/6/2021 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/6/2021 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 4/13/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 4/13/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 4/13/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 4/13/2021 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/13/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 6/3/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 6/3/2021 | Permit Finaled | HAMIK HARTOUNIAN |
| HVAC-Final | 6/3/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 6/3/2021 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 6/3/2021 | Approved | HAMIK HARTOUNIAN |